( )is a process of monitoring the status of the project to update the project costs and manage changes is the cost baseline.A.Plan Cost ManagementB.Estimate CostsC.Determine BudgetD.Control costs

( )is a process of monitoring the status of the project to update the project costs and manage changes is the cost baseline.

A.Plan Cost Management
B.Estimate Costs
C.Determine Budget
D.Control costs

参考解析

解析:控制成本是一个监控项目状态的过程,目的是更新项目成本并且对成本基准的变化进行管理。
2019年11月软考(系统集成项目管理工程师)综合知识真题答案

◇2019年11月软考(系统集成项目管理工程师)综合知识真题答案
若本套试卷含有主观题,针对主观题请自行参考解析评分
单项选择题
一、单项选择题(共75道题,每道题1.0分。)

相关考题:

The reason that cost management is so difficult in project management is that:A . Projects by definition and nature are non-recurring events and are therefore difficult to predict.B . There are no tools for identifying project tasks.C . Project managers do not care about tracking costs, as only schedules are important to all project managers.D . A and B onlyE . B and C only

Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A . Baseline costsB . Budgeted costs.C . Estimates upon completion costsD . Scheduled costsE . None of the above

Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:A . Overhead rates, labor rates and material costs.B . Overhead rates, schedule slippages, and rework.C . Rework, cost-of-living adjustments, and overtime.D . Material costs, shipping cost, and scope changes.E . Labor rates, material costs, and cost reporting.

A Project Status Report would include all of the following except:A Cost and schedule reportsB Changes to scope. cost or scheduleC Narrative explanation of variancesD Personnel problems on the projectE Upcoming activities

Amount at Stake is the _____ .A function of planned time/real time project costs.B risk identified in successful project completions.C (Standard Project Deviation + Expected Costs)/6D cost of investment loss + least cost to restore status quo.E inherent risk at conception altered by standard project deviations.

144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:A. Overhead rates, labor rates and material costs.B. Overhead rates, schedule slippages, and rework.C. Rework, cost-of-living adjustments, and overtime.D. Material costs, shipping cost, and scope changes.E. Labor rates, material costs, and cost reporting

185 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above

95 A Project Status Report would include all of the following except:A. Cost and schedule reportsB. Changes to scope. cost or scheduleC. Narrative explanation of variancesD. Personnel problems on the projectE. Upcoming activities

You are working on the cost budget for one project. Which of the following is true() A.This process assigns cost estimates to project activities including risks and contingency plans.B.The cost baseline will be used to measure variances and future project performance.C.This process assigns cost estimates for expected future period operating costs.D.The cost baseline is the expected cost for the project.

67 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above.

The(69)Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.A.PlannlngB.ExecutingC.Monitoring and ControllingD.Closing

The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out

Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project

● Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(75) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.(75)A.Cost-Benefit analysisB.Control chartsC.Quality function deploymentD.Cost of quality analysis

The key benefit of ( )is that it provides guidance and direction on how the project costs will be managed throughout the project.A.Plan Cost ManagementB.Control CostC.Estimate CostD.Determine Budget

Plan Quality is the process of identifying quality requirements and standards for the project and product and documenting how the project will demonstrate compliance ______ is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement and failing to meet requirements.A.Cost-Benefit analysisB.Control chartsC.Quality function deploymentD.Cost of quality analysis

All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approveD.by managementD.Manage changes as they occur

( )is a process developing a document that formally authorizes the existence of a project and provides theproject manager with the authority to apply organizational resources to project activities.A.Develop Project CharterB.Manage Project KnowledgeC.Monitor and Control Project workD.Close project

The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.A.Plan Cost Management B.Control CostC. Estimate CostD. Determine Budget

A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.taskB.workC.sequenceD.activity

Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of the A.project scope statement B.statement of work C.project management plan D.project policy

( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.A.Develop Project CharterB.Manage Project KnowledgeC.Monitor anD.Control Project workD.Close project

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.A、PlanningB、ExecutingC、Monitoring and ControllingD、Closing

You are working on the cost budget for one project. Which of the following is true()A、This process assigns cost estimates to project activities including risks and contingency plans.B、The cost baseline will be used to measure variances and future project performance.C、This process assigns cost estimates for expected future period operating costs.D、The cost baseline is the expected cost for the project.

Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.空白(3)处填()A、project scope statementB、statement of workC、project management planD、projectpolicy

单选题You are working on the cost budget for one project. Which of the following is true()AThis process assigns cost estimates to project activities including risks and contingency plans.BThe cost baseline will be used to measure variances and future project performance.CThis process assigns cost estimates for expected future period operating costs.DThe cost baseline is the expected cost for the project.

单选题An example of scope verification is ().Areview the performance ofan installed software moduleBmanaging changes to the project scheduleCdecomposing the WBS to a work package levelDperforming a benefit/cost analysis to determine if we should proceed with the project