( )is a process developing a document that formally authorizes the existence of a project and provides theproject manager with the authority to apply organizational resources to project activities.A.Develop Project CharterB.Manage Project KnowledgeC.Monitor and Control Project workD.Close project

( )is a process developing a document that formally authorizes the existence of a project and provides the
project manager with the authority to apply organizational resources to project activities.

A.Develop Project Charter
B.Manage Project Knowledge
C.Monitor and Control Project work
D.Close project

参考解析

解析:制定项目章程是一个制定正式文件的过程,授权项目的存在,为项目经理提供权限使用组织资源。

相关考题:

The initial document that formally recognizes the existence of a project is the _____ .A.Scope baselineB.Management planC.Project charterD.Configuration control reportE.None of the abov

The project charter is a document designed to tell _____ exactly what the project entails.AThe project managerBThe project officeCThe project teamDThe project sponsorEAnyone associated with the project

The use of the project reports:A.are not necessary on small projectsB.provides a means whereby various levels of authority can judge project performanceC.provides insight into project areas and the effectiveness of the control systemsD.All of the aboveE.B and C

What is the purpose of the Project Plan?A.To document the Preliminary estimates.B.To document the Definitive estimates.C.To document the Budgetary estimates.D.To document Parametric estimates.E.To document Order of Magnitude estimates.

The primary source document for establishing the content of the Project Status Report is:A The project charterB The Project PlanC The ASTM Project Document GuideD The summary work breakdown structure

139 The project charter is a document designed to tell _____ exactly what the project entails.A. The project managerB. The project officeC. The project teamD. The project sponsorE. Anyone associated with the project

94 The primary source document for establishing the content of the Project Status Report is:A. The project charterB. The Project PlanC. The ASTM Project Document GuideD. The summary work breakdown structure

145 The initial document that formally recognizes the existence of a project is the _____ .A. Scope baselineB. Management planC. Project charterD. Configuration control reportE. None of the above

● The initial document that formally recognizes the existence of a project is the _____ .A Scope baselineB Management planC Project charterD Configuration control reportE None of the above

● The use of the project reports:A are not necessary on small projectsB provides a means whereby various levels of authority can judge project performanceC provides insight into project areas and the effectiveness of the control systemsD All of the aboveE B and C

● What is the purpose of the Project Plan?A To document the Preliminary estimates.B To document the Definitive estimates.C To document the Budgetary estimates.D To document Parametric estimates.E To document Order of Magnitude estimates.

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend

●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend

The( )provides the project manager with the authority to apply organizational resources to project activities。A.project management planB.project charterC.project human resource planD.project stakeholders

Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project

●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.(75) A. Resource assignment matrixB. Change control planC. Project charterD. Client organization chart

The (73) provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.project charterC.project human resource planD.project stakeholders

()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.A.The project charterB.The project scope statementC.The WBS dictionaryD.The activity list

( )is a process of developing a detailed description of the project and productA.collect requirementsB.Definition scopeC.validate scopeD.Control range

When required the perform Integrated Change Control Process includes ()Which is a formally chartered group responsible for reviewing ting approving deferring or rejecting changes to the project and for ing and communicating such decisionsA.BBC]B.CCB]C.BCB]D.CBC]

A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.taskB.workC.sequenceD.activity

( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.A.Develop Project CharterB.Manage Project KnowledgeC.Monitor anD.Control Project workD.Close project

Your have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information. A.Resource assignment matrix B.Change control plan C.Project charter D.Client organization chart

The inputs of developing project management plan do not include()A、project charterB、stakeholder management strategyC、project scope statementD、outputs from planning processes

The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、project charter

The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、projectcharter

单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.AanalyzeBtrackClevelDextend