( )Estimating current project costs by analogy with similar projects。( )是以类似的项目进行类比估计当期项目的费用。A.Top-down estimating自上而下估算法B.Parametric model method参数模型法C.Bottom-up estimation metho从下向上的估计法D.Computing Tool Aided Method计算工具辅助的方法

( )Estimating current project costs by analogy with similar projects。
( )是以类似的项目进行类比估计当期项目的费用。

A.Top-down estimating
自上而下估算法
B.Parametric model method
参数模型法
C.Bottom-up estimation metho
从下向上的估计法
D.Computing Tool Aided Method
计算工具辅助的方法

参考解析

解析:“自上而下估算法”。这种方法的基本操作步骤是:(1)监理项目组的高层次管理人员收集以往类似项目的有关历史资料;(2)会同有关成本方面的专家对当前项目的总成本进行估算;(3)将估算结果按照项目工作分解结构图的层次结构传递给下层的项目监理人员,在此基础上,他们对自己所负责的工作和活动的成本进行估计;(4)继续向下一层监理人员传递估计信息。从步骤可以看出,自上而下估算法,是依据类似项目,进行估算当期项目的费用。

相关考题:

A program can best be described as:AA grouping of related activities which last two years or moreBThe first major subdivision of a projectCA grouping of projects, similar in nature, which support a product or product line and have no definable end pointDA product lineEAnother name for a project

Parametric estimates are based on variables such as:A.Detailed planning and cost restraints.B.Physical characteristics and historical data.C.The WBS and similar projects.D.Project objectives and manpower allocations.E.Precise measurements and multiple inputs.

The reason that cost management is so difficult in project management is that:A . Projects by definition and nature are non-recurring events and are therefore difficult to predict.B . There are no tools for identifying project tasks.C . Project managers do not care about tracking costs, as only schedules are important to all project managers.D . A and B onlyE . B and C only

Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.A . Definitive, bottom up.B . Analogy, top down.C . Parametric, bottom up.D . Parametric, top down.E . Analogy, bottom up.

Which of the following would most likely increase the accuracy of estimating the project cost?A . Pricing out the work at lower levels in the work breakdown structure.B . Using historical data.C . Talking to people who have worked on similar projects.D . All of the above.E . A and C only.

87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.B. Using historical data.C. Talking to people who have worked on similar projects.D. All of the above.E. A and C only.

28 The reason that cost management is so difficult in project management is that:A. Projects by definition and nature are non-recurring events and are therefore difficult to predict.B .There are no tools for identifying project tasks.C. Project managers do not care about tracking costs, as only schedules are important to all project managers.D. A and B onlyE. B and C only

50 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.A. Definitive, bottom up.B. Analogy, top down.C. Parametric, bottom up.D. Parametric, top down.E. Analogy, bottom up.

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.time estimatingB.cost estimatingC.project planningD.schedule development

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

Which function is NOT served by building a prototype?A.It takes the place of the final system.B.It assists in gathering software requirements.C.It assists in estimating the cost of the project.D.It is used as the foundation of the larger projects.

Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.A.accuracyB.approximationC.specificationD.summary

Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.A.accuracyB.approxinationC.specificationD.summary

On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.project planningB.time estimatingC.cost estimatingD.schedule development

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.A.ParametricB.AnalogousC.Three-pointD.Expert judgment

( )are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated equitably over multiple projects by some approved and documented accounting procedure( )是指不能直接追溯到特定项目的成本,因此将通过一些批准和记录的会计程序在多个项目上平均累计和分配。A.Direct costs直接成本B.Operation costs运营成本C.Indirect costs间接成本D.Implement costs实施成本

()is a technique for estimating the duration or cost of activity or a projecy using historical data orm a similar activity or project.A.Analogous estimatingB.Parametric estimatingC.Three-Point estmatingD.Bottom-Up estimating

Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of the A.project scope statement B.statement of work C.project management plan D.project policy

Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating B.activity resource estimating, activity duration estimating, schedule development C.schedule developing, activity resource estimating, activity duration estimating D.activity resource estimating, schedule developing, activity duration estimating

()are?those?costs?that?cannot?be?directly?traced?to?a specific?project?and?therefore?will?be?accumulated?and allocated?equitably?over?multiple?projects?by?some?approved and?documented?accounting?procedure.A.Direct costsB.Operation costsC.Indirect costsD.Implement costs

The () technique involves using project characteristics in a mathematical modelto predict total project costs. Models can be simple or complex. A.Cost Aggregation B.Reserve Analysis C.ParametriC.Estimating D.Funding Limit Reconciliation

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project. A.Parametric B.Analogous C.Three-point D.Expert judgment

Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.空白(3)处填()A、project scope statementB、statement of workC、project management planD、projectpolicy

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A、time estimatingB、cost estimatingC、project planningD、schedule development

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating

单选题Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.空白(2)处填()AactivityBworkCcurrencyDtime