( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project. A.Parametric B.Analogous C.Three-point D.Expert judgment

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

A.Parametric
B.Analogous
C.Three-point
D.Expert judgment

参考解析

解析:类比估计是一项使用类似的活动或项目的历史数据,来估计活动的时间或成本的技术。 (73) A.参数 B.类比 C.三点 D.专家判断

相关考题:

Sources for data on activity durations and resource requirements can be gathered from which of the following:A.Past project records (historical data)B.Commercial techniques (standard practices, rules of thumb)C.Past project team members knowledge (experience, oldtimers)D.All of the aboveE.A and C only

Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A . PB . QC . RD . SE . T

Which of the following would most likely increase the accuracy of estimating the project cost?A . Pricing out the work at lower levels in the work breakdown structure.B . Using historical data.C . Talking to people who have worked on similar projects.D . All of the above.E . A and C only.

87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.B. Using historical data.C. Talking to people who have worked on similar projects.D. All of the above.E. A and C only.

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

151 Sources for data on activity durations and resource requirements can be gathered from which of the following:A. Past project records (historical data)B. Commercial techniques (standard practices, rules of thumb)C. Past project team members knowledge (experience, oldtimers)D. All of the aboveE. A and C only

● Sources for data on activity durations and resource requirements can be gathered from which of the following:A Past project records (historical data)B Commercial techniques (standard practices, rules of thumb)C Past project team members knowledge (experience, oldtimers)D All of the aboveE A and C only

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.time estimatingB.cost estimatingC.project planningD.schedule development

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.A.milestoneB.baselineC.qualityD.work

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.A.accuracyB.approximationC.specificationD.summary

Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.A.accuracyB.approximationC.specificationD.summary

Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.A.accuracyB.approxinationC.specificationD.summary

On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.project planningB.time estimatingC.cost estimatingD.schedule development

During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate This duration is what you commit to complete the project. What is wrong with the scenario? ()A.The team did not create the estimate and estimating tales too long using that methodB.The team did not create the estimate and a network diagram was not usedC.The estimate is too long and should be created by managementD.The project estimate should be the same as the customer's required completion date

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.A.ParametricB.AnalogousC.Three-pointD.Expert judgment

()is a technique for estimating the duration or cost of activity or a projecy using historical data orm a similar activity or project.A.Analogous estimatingB.Parametric estimatingC.Three-Point estmatingD.Bottom-Up estimating

Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of the A.project scope statement B.statement of work C.project management plan D.project policy

Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating B.activity resource estimating, activity duration estimating, schedule development C.schedule developing, activity resource estimating, activity duration estimating D.activity resource estimating, schedule developing, activity duration estimating

The () technique involves using project characteristics in a mathematical modelto predict total project costs. Models can be simple or complex. A.Cost Aggregation B.Reserve Analysis C.ParametriC.Estimating D.Funding Limit Reconciliation

Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.A、milestoneB、baselineC、qualityD、work

Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.空白(3)处填()A、project scope statementB、statement of workC、project management planD、projectpolicy

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A、time estimatingB、cost estimatingC、project planningD、schedule development

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating

单选题On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.Atime estimatingBcost estimatingCproject planningDschedule development

单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.Aactivity duration estimating, schedule developing, activity resource estimatingBactivity resource estimating, activity duration estimating, schedule developmentCschedule developing, activity resource estimating, activity duration estimatingDactivity resource estimating, schedule developing, activity duration estimating

单选题Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.空白(2)处填()AactivityBworkCcurrencyDtime