87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.B. Using historical data.C. Talking to people who have worked on similar projects.D. All of the above.E. A and C only.

87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.

B. Using historical data.

C. Talking to people who have worked on similar projects.

D. All of the above.

E. A and C only.


相关考题:

In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.A.Increase, decrease.B.Increase, increaseC.Increase, increase or decrease.D.Decrease, decrease.E.Decrease, increase.

Time management is the allocation of time in a project's life cycle through the process of:A.PlanningB.Estimating.C.Scheduling.D.ControllingE.All of the above.

Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.A . Increase, increase.B . Increase, decrease.C . Decrease, decrease.D . Decrease, increase.E . Remain the same, return to customer.

185 In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.A. Increase, decrease.B. Increase, increaseC. Increase, increase or decrease.D. Decrease, decrease.E. Decrease, increase

6 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.A. Increase, increase.B. Increase, decrease.C. Decrease, decrease.D. Decrease, increase.E. Remain the same, return to customer

67 In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.A. Increase, decrease.B. Increase, increaseC. Increase, increase or decrease.D. Decrease, decrease.E. Decrease, increase

88 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.A. Increase, increase.B. Increase, decrease.C. Decrease, decrease.D. Decrease, increase.E. Remain the same, return to customer

196. Shoppers who carefully plan their visit to the grocery store can save money on their grocery bills. Shopping when not hungry, sticking to their grocery list, and _1_ a few simple rules will cut down the grocery bill. Shoppers should visit the grocery store on a full stomach by planning their trip _2_ after a large meal. If that’s not possible, they should find something healthy to eat on while preparing a grocery list. Most shoppers are less _3_ to buy extras when they are not troubled by hunger. Although having a list and _4_ to it is the most important factor in saving money, shoppers must prepare lists wisely in order to save. A carefully planned list should _5_ in season produce and any items on sale or discount through coupons. Many special buys are announced through the local newspapers, so buying the “grocery issue” is _6_ the money you spend. What’s more, it’s important to remember that many newer, more expensive products first offered through coupons may not _7_ enough savings for shoppers to give up products they usually buy. Now that the shopper has _8_ the grocery list, it’s time to leave for the store. However, no preparations are complete without a pocket calculator or a piece of paper and a pencil to figure costs. Once at the store, the shopper who wants to save money should follow a few more rules. The shoppers should not stay _9_ than necessary because bills go up each minute the shopper is in the store. So, _10_ a time limit and a cost limit can hold down the bill. [共10题](1)(A) carrying (B) making (C) taking (D) following(2)(A) recently (B) regularly (C) immediately (D) completely(3)(A) willingly (B) likely (C) reluctantly (D) happily(4)(A) sticking (B) replying (C) according (D) belonging(5)(A) keep (B) make (C) increase (D) include(6)(A) worth (B) suitable (C) value (D) fit(7)(A) come from (B) result in (C) succeed in (D) depend on(8)(A) saw (B) taken (C) completed (D) read(9)(A) shorter (B) faster (C) longer (D) quicker(10)(A) setting (B) putting (C) making (D) taking

The more seriously this is sought,______(likely)positive attitudes towards leisure as well as academic work will be encouraged.

You’re going to have a quiz ( )by another two in the ( )month. A. followed,followedB. followed,followingC. following,followedD. following,following