The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)A.change control boardB. project management officeC.project managerD.configuration management officer

The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)

A.change control board

B. project management office

C.project manager

D.configuration management officer


相关考题:

The purpose of configuration management is to:A.insure drawings are updatedB.control change throughout the projectC.control change during the production onlyD.generate engineering change proposalsE.inform. the project manager of changes

Scope management is:A.a project control function.B.employs change control.C.a work authorization process.D.considers Cost, Quality and Schedule.E.All of the above.

33 The purpose of configuration management is to:A. insure drawings are updatedB. control change throughout the projectC. control change during the production onlyD. generate engineering change proposalsE. inform. the project manager of changes

66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A. Change the scope baselineB. Prepare a variance reportC. Call a meeting of the configuration control boardD. Change the project's objectivesE. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A Change the scope baselineB Prepare a variance reportC Call a meeting of the configuration control boardD Change the project's objectivesE Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

● The purpose of configuration management is to:A insure drawings are updatedB control change throughout the projectC control change during the production onlyD generate engineering change proposalsE inform. the project manager of changes

● Scope management is:A a project control function.B employs change control.C a work authorization process.D considers Cost, Quality and Schedule.E All of the above.

● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .(73) A. change the scope baselineB. contact the customer to determine if the change adds valueC. call a meeting of the change control boardD. change the project' s objectives

A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

You develop a Web control. The Web control consists of labels and associated text boxes.You need to ensure that the Web control has both toolbox and visual designer support. What should you do?() A. Add a Web Control Library project to your solution. Define a class that inherits from CompositeControl.B. Add a Windows Control Library project to your solution. Define a class that inherits from UserControl.C. Add a Web User Control to your project. Define a class that inherits from UserControl.D. Add a Mobile Web User Control to your project. Define a class that inherits from MobileUserControl.

The perform. Integrated Change Contorl process is the ultimate responsibility of the(①).Although changes may be initiated verbally,they should be recorded in writtern form. and entered into the (②)system.①A.resource managerB.division managerC.functional managerD.project manager②.A.quality managementB.configuration managementC.project managerD.scope management

●Ravi, like many project (71) ,had studied the waterfall model of software development as the primary software life-cycle (72) .He was all set to use it for an upcoming project, his first assignment. However, Ravi found that the waterfall model could not be used because the customer wanted the software delivered in stages, something that implied that the system had to be delivered and built in (73) and not as (74) .The situation in many other projects is not very different. The real world rarely presents a problem in which a standard process, or the process used in a previous project, is the best choice.To be the most suitable, an existing process must be (75) to the new problem.Adevelopment process, even after tailoring, generally cannot handle change requests. To accommodate change requests without losing control of the project, you must supplement the development process with a requirement change management process.(71) A.customers B.managers C.users D.administrators(72) A.activity B.procedure C.process D.progress(73) A.parts B.modules C.software D.a whole(74) A.parts B.modules C.software D.a whole(75) A.modified B.used C.suited D.tailored

Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).A.change the scope baselineB.contact the customer to determine if the change adds valueC.call a meeting of the change control boardD.change the project’s objectives

A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline

Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( ) A.change the scope baselineB.contact the customer to determine if the change adds valueC.call A.meeting of the change control boardD.change the project's objectives

The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .实施整体变更控制过程是从项目开始到项目结束并且是( )项目经理的最终责任。A.Chang control board变更控制委员会B.Project management office项目管理办公室C.Project manager项目经理D.Configuration management officer配置管理员

The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) . A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer

( )is a process developing a document that formally authorizes the existence of a project and provides theproject manager with the authority to apply organizational resources to project activities.A.Develop Project CharterB.Manage Project KnowledgeC.Monitor and Control Project workD.Close project

( )is not included in Perform Integrated Change Control Process.A.Defining subsidiary plansB.Approving changesC.Managing changes to deliverablesD.Reviewing all change requests

The project management plan defines how the project is executed,monitored and controlled,and closed.It is progressively elaborated by updates,and controlled and approved through the perform integrated( )process.A.Cost controlB.Schedule controlC.Change controlD.Risk control

When required the perform Integrated Change Control Process includes ()Which is a formally chartered group responsible for reviewing ting approving deferring or rejecting changes to the project and for ing and communicating such decisionsA.BBC]B.CCB]C.BCB]D.CBC]

Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT managerB.project mangerC.change control boardD.project sponsor

( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.A.Develop Project CharterB.Manage Project KnowledgeC.Monitor anD.Control Project workD.Close project

( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project. A.Integrated management B.Configuration management C.Scope management D.Requirements management

( ) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.A、Integrated managementB、Configuration managementC、Scope managementD、Requirements management

单选题Ravi, like many project (1) , had studied the waterfall model of software development as the primary software life-cycle (2) . He has all set to use it for an upcoming project, his first assignment. However, Ravi found that the waterfall model could not be used because the customer wanted the software delivered in stages, something that implied that the system had to be delivered and built in (3) and not as (4) . The situation in many other projects is not very different. The real world rarely presents a problem in which a standard process, or the process used in a previous project, is the best choice. To be the most situation, an existing process must be (5) to the new problem. A development process, even after tailoring, generally cannot handle change requests. To accommodate change requests without losing control of the project, you must supplement the development process with a requirement change management process.空白(2)处应选择()AactivityBprocedureCprocessDprogress

单选题You develop a Web control. The Web control consists of labels and associated text boxes.You need to ensure that the Web control has both toolbox and visual designer support. What should you do?()AAdd a Web Control Library project to your solution. Define a class that inherits from CompositeControl.BAdd a Windows Control Library project to your solution. Define a class that inherits from UserControl.CAdd a Web User Control to your project. Define a class that inherits from UserControl.DAdd a Mobile Web User Control to your project. Define a class that inherits from MobileUserControl.