Scope management is:A.a project control function.B.employs change control.C.a work authorization process.D.considers Cost, Quality and Schedule.E.All of the above.
Scope management is:
A.a project control function.
B.employs change control.
C.a work authorization process.
D.considers Cost, Quality and Schedule.
E.All of the above.
相关考题:
The document authorizing functional areas to charge against the project is the:A. Work authorization formB. Scope baselineC. Project charterD. Management planE .Linear responsibility chart
The project life-cycle can be described as:A.project concept, project planning, project execution, and project close-out.B.project planning, work authorization, and project reporting.C.project planning, project control, project definition, WBS development, and project termination.D.project concept, project execution, and project reporting.E.All of the above.
Scope Management:A.entails managing the project's work content.B.is a subset of configuration management and as such is performed by CM specialists.C.is concerned with naming all activities performed, the end products which results and the resources consumed.D.is not a concern of the project manager.E.None of the above.
The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.
The most effective means of determining the cost of a project is to price out the _____.A . Work breakdown structure.B . Linear responsibility chart.C . Project charter.D . Scope statement.E . Management plan.
Quality and _____ are directly related.A . productivityB . cost overrunsC . scope controlD . Pareto diagramE . None of the above.
The best way to insure quality conformance is to _____.A . distribute the responsibility to subordinates.B . maintain total control.C . train each worker to implement the work.D . inspect quality into the project.E . None of the above.
In Project Risk Management, Risk Response may include actions to:A reduce the probability of risk eventsB change the scope, budget, schedule or quality specifications of the projectC reduce the consequences or severity of impacts of a potential risk eventD A and CE All of the above.
By which means is a contractor able to control cost overruns due to changing requirements?A Project data reviewB Change orderC Purchase order amendmentD Change controlE None of the above.
99 Scope management is:A. a project control function.B. employs change control.C. a work authorization process.D. considers Cost, Quality and Schedule.E. All of the above
61 The document authorizing functional areas to charge against the project is the:A. Work authorization form.B. Scope baselineC. Project charterD. Management planE. Linear responsibility chart
● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation
● The document authorizing functional areas to charge against the project is the:A Work authorization formB Scope baselineC Project charterD Management planE Linear responsibility chart
● Scope Management:A entails managing the project's work content.B is a subset of configuration management and as such is performed by CM specialists.C is concerned with naming all activities performed, the end products which results and the resources consumed.D is not a concern of the project manager.E None of the above.
● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.
● Scope management is:A a project control function.B employs change control.C a work authorization process.D considers Cost, Quality and Schedule.E All of the above.
The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteriaA.work performance informationB.scope statementC.change requestsD.process analysis
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
“Cost of quality”is a project management concept that includes cost of( 73)A.exceedings requirementsB.Changes to the requirementsC.Ensuring conformance to requirementsD.The quality control requirements
The Project Management Triangle is a model of the constraints of project management. These constraints have been listed scope (or quality),(), and cost.A.resourceB.timeC.planD.tool
The Project Management Triangle is a model of the constraints of projectmanagement.These constraints have been listed scope(or quality),(73),and cost.A.resourceB.time C.planD.tool
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopEB:Project stakeholder managementC:Project scope managementD:Project cost management
Much of the effort cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures . The key to effective cost control is the management of the approved ( ) .A.Schedule baselineB.Cost baselineC.Cost outputD.Cost input
( )is not included in Control Quality input documents.A.Project management planB.Project documentsC.Quality problems reportD.Work performance data
( )in not inc1uded in Control Quality input documents.A.Project management planB.Project documentsC.Quality problems reportD.Work performance data
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopEB. Project stakeholder managementC. Project scope managementD. Project cost management
( ) is primarily concerned with defining and controlling what is and is not included in the project. A.Project Time Management B.Project Cost Management C.Project Scope Management D.Project Communications Management