● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A Change the scope baselineB Prepare a variance reportC Call a meeting of the configuration control boardD Change the project's objectivesE Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project's objectives
E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
相关考题:
● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.(71)A.riskB.problemC.resultD.data
Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
以下关于Openstack租户Project说法错误的是()。 A、一个Project资源集合可供多个用户使用B、Project是Openstack各个服务中的一些可以访问的资源集合C、网络云各Project采用硬件共享,逻辑隔离的方式D、租户是一个有身份验证信息的API实体
Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
中国青少年发展基金会在网上的主页地址是()。 A.http://project-hopE.cydF.gov.cnB.http://project-hopE.cydF.acC.http://project-hopE.cydF.edu.cnD.http://project-hopE.cydF.com.cn
Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.A.riskB.problemC.resultD.data
Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
在对原理图进行电气规则检查前,可以()打开规则设置界面。A.design-Document OptionsB.Project-Project OptionsC.Tools-Schematic PreferencesD.Project-Configuration Manager
以下选项中哪个选项是根路径的表达方法?A.D:/Program Files/.Net/Project1B./root/.Net/Project1C../home/.Net/Project1D.file://D:/Program Files/.Net/Project1