Deviation changes with a change in ______.A.latitudeB.headingC.longitudeD.sea conditions

Deviation changes with a change in ______.

A.latitude

B.heading

C.longitude

D.sea conditions


相关考题:

The purpose of configuration management is to:A.insure drawings are updatedB.control change throughout the projectC.control change during the production onlyD.generate engineering change proposalsE.inform. the project manager of changes

During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:A.Now becomes the new schedule, including the changes, and the original baseline is disregarded.B.Is still the original baseline but annotated to reflect that a change has taken place.C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.D.Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)E.Is the same since baseline schedules cannot change once the development phase is completed.

33 The purpose of configuration management is to:A. insure drawings are updatedB. control change throughout the projectC. control change during the production onlyD. generate engineering change proposalsE. inform. the project manager of changes

● The purpose of configuration management is to:A insure drawings are updatedB control change throughout the projectC control change during the production onlyD generate engineering change proposalsE inform. the project manager of changes

● During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.(75)A. proceedingsB. controlsC. forecasting’sD. prelibations

● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).(73)A.executive IT managerB.project mangerC.change control boardD.project sponsor

When making changes to a server, which of the following is the BEST way to troubleshoot a problem?() A. Perform root cause analysis and then test the theory to determine the cause.B. Make changes to the system and document everything once the problem is resolved.C. Make multiple changes to all affected areas to resolve all potential issues.D. Make a change and if the problem is not resolved, reverse the change.

management includes negotiating the terms and conditions in contracts and ensuring compliance with the terms and conditions,as well as documenting and agreeing on any changes or amendments that may arise during its implementation or executionA.ContractB.DocumentC.CommunicationD.Risk

During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised(75)are necessary.A.proceedingsB.controlsC.forecasting'sD.prelibations

材料:Intention can be inferred in many ways by the courts.Thus the discharge at Cadiz instead of Bombay“for nefarious reasons”was an unreasonable deviation.A transshipment was declared to be an unreasonable deviation “since no excuse has been proffered for the deviation.” A geographic deviation abrogated the contract because“there can be no suggestion that the deviation was other than voluntary.”On the other hand,where the court was unable to find that a defendants action constituted“a voluntary deviation without reasonable cause,” the defendant was exculpated of liability.The vast majority of decisions require that intention be proved in cases of deviation and quasi-deviation.The carrier has the burden of proving that it had no intention to deviate or that the deviation was not for the carriers sole benefit.Accordingly,a geographic deviation due to an erroneous change of course by the master is not a deviation,but an error in navigation;in such a case,the carrier is protected under the Rules.If,however,the master is ordered to alter the customary or planned route,or deliberately takes it upon himself to do so,for a reason other than to save persons or cargo(or some similar reason),then the course alteration is an unreasonable deviation,because it is intentional and for the carriers own benefit.nefarious,邪恶的,穷凶极恶的proffer,提出abrogate,使作废问题:If the carrier has proved that he had no intention to deviate or that the deviation was not for his sole benefit ________.A.he will be exculpated of liabilityB.he is to investigate the case furtherC.he will not be exculpated of liabilityD.he has to contact with the shipper to see if he himself is free of any liabilityA geographic deviation due to an erroneous change of course by the master ________.A.is not a reasonable deviationB.is not an error in navigationC.is a reasonable deviationD.can not be determined if it constitutes a reasonable deviationWhere the court is unable to find that a defendant's action constituted “a voluntary deviation without reasonable cause,”________.A.the defendant will not be responsible for the loss and damageB.the defendant will be responsible for the loss and damageC.if the defendant be responsible for the loss and damage can not be determinedD.the court should not make any decisionAn unreasonable deviation must be committed by the master ________.A.intentionallyB.for the carrier's own benefitC.intentionally and for the carrier's own benefitD.reasonably请帮忙给出每个问题的正确答案和分析,谢谢!

All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approveD.by managementD.Manage changes as they occur

( ) management includes negotiating the terms and conditions in contracts and ensuring compliance with. the terms and conditions, as well as documenting and agreeing on any changes or amendments that may arise during its implementation or execution. A.Contract B.Document C.CommunicationD.Risk

( )is not included in Perform Integrated Change Control Process.A.Defining subsidiary plansB.Approving changesC.Managing changes to deliverablesD.Reviewing all change requests

Change management would typically be composed of the raising and recording of changes, assessing the impact, cost, benefit and risk of proposed changes,developing business justification and obtaining approval, managing and coordinating change implementation, monitoring and reporting on implementation, reviewing and closing (). A. change reason B. change modelC. remediation planD. change requests

Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) . A.executive IT manager B.project manger C.change control board D.project sponsor

Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT managerB.project mangerC.change control boardD.project sponsor

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()A、executive IT managerB、projectmangerC、change control boardD、projectsponsor

Which statement correctly describes the change tracking writer (CTWR) background process?()A、 It keeps track of changes in the background processes.B、 It records the system change number (SCN) in the control file.C、 It writes audit records for user changes to the change tracking file.D、 It records any changes to the listened configuration in the listener.ora file.E、 It records any changes to the database parameters in the change tracking file.F、 It records the physical location of all the changes that are made to the database in the change tracking file.

When making changes to a server, which of the following is the BEST way to troubleshoot a problem?()A、 Perform root cause analysis and then test the theory to determine the cause.B、 Make changes to the system and document everything once the problem is resolved.C、 Make multiple changes to all affected areas to resolve all potential issues.D、 Make a change and if the problem is not resolved, reverse the change.

单选题Deviation changes with a change in().AlatitudeBheadingClongitudeDsea conditions

单选题When making changes to a server, which of the following is the BEST way to troubleshoot a problem?()A Perform root cause analysis and then test the theory to determine the cause.B Make changes to the system and document everything once the problem is resolved.C Make multiple changes to all affected areas to resolve all potential issues.D Make a change and if the problem is not resolved, reverse the change.

单选题The compass deviation changes as the vessel changes().Ageographical positionBspeedCheadingDlongitude

单选题When conditions change with time, we should revise our policies_____.AaccordinglyBconsequentlyCpresumablyDpreliminarily

单选题Magnetic variation changes with a change in().Athe vessel's headingBsea conditionsCseasonsDthe vessel's position

单选题The vertical component of the Earth’s magnetic field causes induced magnetism in vertical soft iron. This changes with latitude. What corrects for this coefficient of the deviation? ()AThe Flinders barBThe heeling magnetCQuadrantal soft iron spheresDBar magnets in the binnacle

单选题Inductance is the property of an electric circuit that ()Aopposes any change in the applied voltageBopposes any change in the current flow through the circuitCaids any changes in the applied voltageDaids any changes in the current through the circuit

单选题During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.AproceedingsBcontrolsCforecastingsDPrelibations