● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).(73)A.executive IT managerB.project mangerC.change control boardD.project sponsor
● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).
(73)
A.executive IT manager
B.project manger
C.change control board
D.project sponsor
相关考题:
Some of them did not get a chance to see the Olympic flame because of the () changes, but we, indeed, feel their passion for China and the Olympics. A.profitB.suspendC.escapeD.route
Reducing the gap between rich and poor is one of the main _______ facing the government.A、chancesB、challengesC、chainsD、changes
WhattwostatementsaretrueaboutOracleEnterpriseManager’sJavaDiagnostictool,whichmakesthetoolsuitableforproductionserverdiagnostics?() A.virtuallyzerooverheadforapplicationrunningintheJVMB.nostallingofrunningJVMwhentakingaheapdumpformemoryanalysisC.noneedofmodification,changes,orinstrumentationoftheapplicationsinceisusesNetworkProtocolAnalysis(NPAtechnology)D.providesByteCodeInstrumentationforJava
The process of choosing names______ widely from culture to culture.A.shiftsB.variesC.differsD.changes
The price of vegetables varies according to the weather.A: jumpsB: risesC: fallsD: changes