单选题During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.AproceedingsBcontrolsCforecastingsDPrelibations

单选题
During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.
A

proceedings

B

controls

C

forecastings

D

Prelibations


参考解析

解析: 该题的关键词为"appropriate measures、 requirements volatility",其语句结构为"The project manager(主{吾) may, however, want to track(谓{吾) appropriate measures of requirements volatility(宾语) to judge whether new or revised()are necessary(目的状语从句)",含义为"项目经理也许会跟踪需求变化的相关度量,以判断是否应该调整的或者新的什么",因为整段文字讨论的内容都集中于需求变更管理,所以只分析最后一句即可,根据题意,应该在空白处填写"措施"一类的词汇,排除之后只有选项B比较适合,选项A、C和D都可以排除,尤其是选项D是一个很生僻的词汇,含义为"尝试"。

相关考题:

The purpose of configuration management is to:A.insure drawings are updatedB.control change throughout the projectC.control change during the production onlyD.generate engineering change proposalsE.inform. the project manager of changes

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(73)A. work performance informationB. scope statementC. change requestsD. process analysis

By which means is a contractor able to control cost overruns due to changing requirements?A Project data reviewB Change orderC Purchase order amendmentD Change controlE None of the above.

The "buy or make" decision is usually made during the:A acquisition cycleB contract evaluation cycleC requirements cycleD pre-award cycleE at any time that is convenient for the project manager

139 By which means is a contractor able to control cost overruns due to changing requirements? A. Project data reviewB. Change orderC. Purchase order amendmentD. Change controlE. None of the above

33 The purpose of configuration management is to:A. insure drawings are updatedB. control change throughout the projectC. control change during the production onlyD. generate engineering change proposalsE. inform. the project manager of changes

● The purpose of configuration management is to:A insure drawings are updatedB control change throughout the projectC control change during the production onlyD generate engineering change proposalsE inform. the project manager of changes

● The project maintains a current and approved set of requirements ovethe life of the project by doing the following:· (73) all changes to the requirements· Maintaining the relationships among the requirements, the project plansand the work products· ……(73)A. MonitoringB. ManagingC. GatheringD. Reducin

● During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.(75)A. proceedingsB. controlsC. forecasting’sD. prelibations

● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).(73)A.executive IT managerB.project mangerC.change control boardD.project sponsor

The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteriaA.work performance informationB.scope statementC.change requestsD.process analysis

Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.A.accuracyB.approximationC.specificationD.summary

The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out

The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.A.work performance informationB.scope statementC.change requestsD.process analysis

A requirement is simply a statement of what the system must do or what characteristics it needs to have. Requirements written from the perspective of user and focus on user needs are called( ). Requirements written from the developers perspective and describe how the system will be implemented are called( ). Requirements evolve from detailed statemens of business capabilities that a system should have to detailed statements of the technical way in which the capabilities will be implemented in the new system. Requirements can be either functional or nofunctional in nature. For example, during the analysis phase of travel vehicles sales system, the system that must have the ability to search for available inventory is( ). The requirement that the system should be able to work on any Web browser belongs to( ). That customer personal information is protected in compliance with the Data Protection Act is a requirement of( ).A.operational requirements B.business requirements C.technical requirements D.system requirements A.operational requirements B.business requirements C.technical requirements D.system requirements A.a functional requirements B.a technical requirements C.an operational requirements D.a service requirements A.functional requirements B.technical requirements C.operational requirements D.information requirements A.system constraint B.system performance C.secrity and control D.cultural and political

The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . ……A.MonitoringB.ManagingC.GatheringD.Reducing

During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised(75)are necessary.A.proceedingsB.controlsC.forecasting'sD.prelibations

All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approveD.by managementD.Manage changes as they occur

()describes the configurable items of the project and identifies itcms that will be recorded and updated so that the product of the project tins consistent and operableA.The configuration management planB.The change management planC.The requirements traceability matrixD.The change baseline

During the implementation of the project,the user's environment(business environment,organizational structure,etc.)may change,and the demand for the project may also change.For the changing needs of the project scope,()is the person with real approval power.A.userB.project managerC.CCBD.Project investor

Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) . A.executive IT manager B.project manger C.change control board D.project sponsor

Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT managerB.project mangerC.change control boardD.project sponsor

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()A、executive IT managerB、projectmangerC、change control boardD、projectsponsor

( ) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.A、Integrated managementB、Configuration managementC、Scope managementD、Requirements management

During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.A、proceedingsB、controlsC、forecastingsD、Prelibations

You need to recommend changes to the intranet site that meet the company’s technical requirements.   What should you include in the recommendation?()A、additional application poolsB、additional worker processesC、Failover ClusteringD、Network Load Balancing (NLB)

单选题The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()AUse eConfig to configure and validate each pSeries and p5 system.BEngage Advanced Technical Support to review any outstanding technical issues.CConfirm with the customer that the solution design meets their requirements.DPerform a Pre-Install Solution Assurance Review to validate required power requirements.