Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) . A.executive IT manager B.project manger C.change control board D.project sponsor

Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .

A.executive IT manager
B.project manger
C.change control board
D.project sponsor

参考解析

解析:项目变更可以由执行经理(executive IT manager)、项目管理者(project manager)、项目发起人(project sponsor)等任意项目干系人发起,但只能由变更控制委员会(change control board)授权通过。(73) A.执行经理 B.项目经理 C.变更控制委员会 D.项目发起人

相关考题:

The scope statement providesA . A basis for future decisions about a project.B . A baseline to accomplish verification measures.C . A baseline to evaluate potential scope changes.D . All of the aboveE . B and C only

Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:A . Overhead rates, labor rates and material costs.B . Overhead rates, schedule slippages, and rework.C . Rework, cost-of-living adjustments, and overtime.D . Material costs, shipping cost, and scope changes.E . Labor rates, material costs, and cost reporting.

Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool. A.RationalClearcaseB.QualityFunctionDeploymentC.VisualSourceSafeD.ConcurrentVersions System

● During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.(75)A. proceedingsB. controlsC. forecasting’sD. prelibations

The author predicts that _________.A. advances in new technologies will lead to great changes of societyB. the single invention, the chip, will lead to great changes in societyC. the future picture of the world can only be imagined by looking backD. the use of personal computer and factory robots will be widespread

● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).(73)A.executive IT managerB.project mangerC.change control boardD.project sponsor

● Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74) is not a project configuration management tool.(74)A.Rational ClearcaseB.Quality Function DeploymentC.Visual SourceSafeD.Concurrent Versions System

are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.A.ControlsB.BaselinesC.Project stakeholdersD.Project managers

Only a very delicate thermometer can ________ such tiny changes in temperature in a precise way.A、countB、relateC、measureD、number

According to the author, teenage rebellion ( ).A. may be a false beliefB. is common nowadaysC.existed only in the 1960sD. resulted from changes in families

Network management helps you to(66)the strengths and weaknesses of your network, as well as determine any configuration changes that may be necessary. Any controlled changes to your network and its components-especially configurations, software and(67), can have an effect on its overall efficiency. To maintain control, you need the tools and knowledge to manage all activity that has the potential to affect your(68).A.seeB.knowC.monitorD.control

management includes negotiating the terms and conditions in contracts and ensuring compliance with the terms and conditions,as well as documenting and agreeing on any changes or amendments that may arise during its implementation or executionA.ContractB.DocumentC.CommunicationD.Risk

During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised(75)are necessary.A.proceedingsB.controlsC.forecasting'sD.prelibations

In the last paragraph,the author mainly intends toA.list the necessary changes we ought to makeB.advise US to make any necessary changesC.explain what changes can bringD. explain the process of making changes

All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approveD.by managementD.Manage changes as they occur

Wherever there is matter.There is energy;all changes of matter( )changes in the form of the energy.A.retainB.includeC.involveD.contain

Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes. ( ) is not a project configuration management tool.A.Rational ClearcaseB.Quality Function DeploymentC.Visual SourceSafeD.Concurrent Versions System

Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT managerB.project mangerC.change control boardD.project sponsor

It can be inferred from the passage that( ) A.Dickens’s hatred toward London grew with his age B.Dickens ’s works contributed to some of the changes of London C.Dickens liked to portray only the dark sides of London D.Dickens,a social reformer,was devoted to the changes of London

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.A、Project managersB、Project team membersC、SponsorsD、Project stakeholders

Social changes can often bring about language changes.

单选题() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.AcontrolsBbaselinesCprojectstakeholdersDprojectmanagers

单选题Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.ARationalClearcaseBQualityFunctionDeploymentCVisualSourceSafeDConcurrentVersions System

单选题Inductance is the property of an electric circuit that ()Aopposes any change in the applied voltageBopposes any change in the current flow through the circuitCaids any changes in the applied voltageDaids any changes in the current through the circuit

单选题Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()Aexecutive IT managerBprojectmangerCchange control boardDprojectsponsor

单选题During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.AproceedingsBcontrolsCforecastingsDPrelibations

单选题Which statement is true regarding the Port Aggregation Protocol? ()AConfiguration changes made on the port-channel interface apply to all physical ports assigned to the portchannel interface.BConfiguration changes made on a physical port that is a member of a port-channel interface apply to the port-channel interface.CConfiguration changes are not permitted with Port Aggregation Protocol; instead, the standardized Link Aggregation Control Protocol should be used if configuration changes are required.DThe physical port must first be disassociated from the port-channel interface before any configuration changes can be made.