Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level. A.independent resource B.individual work loaD. C.work milestone D.work package

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.

A.independent resource
B.individual work loaD.
C.work milestone
D.work package

参考解析

解析:WBS(工作分解结构)是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包(work package)的层次。
(75) A.独立资源 B.个人工作负荷 C.工作里程碑 D.工作包

相关考题:

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(73)A. work performance informationB. scope statementC. change requestsD. process analysis

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level() A.independentresourceB.individualworkloadC.workmilestoneD.workpackage

The()describes, in detail, the project's deliverables and the work required to create those deliverables. A.project scope statementB.project requirementC.project charterD.product specification

●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.(74) A. Product scope descriptionB. Project objectivesC. Product specificationD. The project scope statement

● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.(75)A.independent resourceB.individual work loadC.work milestoneD.work package

The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteriaA.work performance informationB.scope statementC.change requestsD.process analysis

______describes,in detail,the project's deliverables and the work required to create those deliverables.A.Product scope descriptionB.Project objectivesC.Stakeholder AnalysisD.The project scope statement

The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.A.work performance informationB.scope statementC.change requestsD.process analysis

● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)(74)A. Scope PlanningB. Scope VerificationC. Scope Change ControlD. Scope Definition

()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.A.The project charterB.The project scope statementC.The WBS dictionaryD.The activity list

The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement

The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.A.project scope statementB.project requirementC.project charterD.product specification

()describees,indetail,the project's deliverables and the work required to create those deliverables. A.Product scope description B.Project objectivesC.Produce specificationD.The project scope statement

Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()A.Scope PlanningB.Scope VerificationC.Scope Change ControlD.Scope Definition

( ) describes,in detail,the project’s deliverables and the work required to create those deliverables. A.Product scope description B.Project objectives C.Stakeholder Analysis D.The project scope statement

The creation of a work breakdown structure(WBS)is the process of ( ) the major project deliverables. A.subdividing B.assessing C.planning D.integrating

The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter B.project scope goal C.project budget D.project scope statement

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resourceB.individual work loadC.work milestoneD.work package

()describes, in detail, the project’s deliverables and the work required to create those deliverables.A、Product scope descriptionB、Project objectivesC、Stakeholder AnalysisD、The project scope statement

() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、projectacceptanceB、scopeverificationC、scopedefinitionD、WBS Creation

The () describes, in detail, the project's deliverables and the work required to create those deliverables.A、project scope statementB、project requirementC、project charterD、product specification

()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificationC、Scope definitionD、WBS Creation

单选题The()describes, in detail, the project's deliverables and the work required to create those deliverables.Aproject scope statementBproject requirementCproject charterDproduct specification

单选题()describes, in detail, the project’s deliverables and the work required to create those deliverables.AProduct scope descriptionBProject objectivesCStakeholder AnalysisDThe project scope statement

单选题The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.Awork performance informationBscope statementCchangerequestsDprocess analysis

单选题The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.AsubdividingBassessingCplanningDintegrating

单选题Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()AindependentresourceBindividualworkloadCworkmilestoneDworkpackage