Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level() A.independentresourceB.individualworkloadC.workmilestoneD.workpackage

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

A.independentresource

B.individualworkload

C.workmilestone

D.workpackage


相关考题:

● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.A.ProcessB.MilestoneC.Work D.Deliverables

Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an elementA.relationshipsB.resourcesC.stakeholdersD.deliverables

from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.A.ProcessB.MilestoneC.WorkD.Deliverables

Configuration management is focused on the specification of both the deliverables and the processes;while( )is focused on identifying,documenting,and approving or rejecting changes to the project documents,deliverables,or baselines.A.cost managementB.change managementC.configuration managementD.capacity management

A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.taskB.workC.sequenceD.activity

A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to(请作答此空).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.specificationB.rulesC.estimatesD.designs

A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the(请作答此空),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.deadlineB.specificationC.expectationD.requirement

A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to(请作答此空)project(s).A.a singleB.a particularC.someD.all

Establishing a project management timetable involves listing milestones,activities,and( )with intended start and finish dates,of which the scheduling of employees may be an element. A.relationships B.resources C.stakeholders D.deliverables

()is a document?generated by the?creating?WBS?process?that?support the WBS,which provides?more?detailed?descriptions?of the components in the?WBS.A.The project?charterB.The?project?scope statementC.The?WBS dictionaryD.The?activity list