单选题()describes, in detail, the project’s deliverables and the work required to create those deliverables.AProduct scope descriptionBProject objectivesCStakeholder AnalysisDThe project scope statement

单选题
()describes, in detail, the project’s deliverables and the work required to create those deliverables.
A

Product scope description

B

Project objectives

C

Stakeholder Analysis

D

The project scope statement


参考解析

解析: 参考答案:D

相关考题:

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level() A.independentresourceB.individualworkloadC.workmilestoneD.workpackage

The()describes, in detail, the project's deliverables and the work required to create those deliverables. A.project scope statementB.project requirementC.project charterD.product specification

Define Activities is the process of identifying the specific actions to be performed to produce the (71).A.project elementsB.work draftsC.work packageD.project deliverables

● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).(71)A. project elementsB. work draftsC. work packageD. project deliverables

●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.(74) A. Product scope descriptionB. Project objectivesC. Product specificationD. The project scope statement

● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.(75)A.independent resourceB.individual work loadC.work milestoneD.work package

______describes,in detail,the project's deliverables and the work required to create those deliverables.A.Product scope descriptionB.Project objectivesC.Stakeholder AnalysisD.The project scope statement

The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables. A、project scope statementB、work packageC、WBSD、project scope plan

● A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called (72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73) , whose purpose is to contain the various pieces of relevant information – feasibility assessments, schedules, needs analysis, and so forth – in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.

Operations( )is a document that describes in detail the processes。A.PaperB.BookC.MenuD.Manual

In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.A.scheduleB.activityC.planD.contractor@@@SXB@@@A.findingB.balanceC.allocationD.distribution

The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement

The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.A.project scope statementB.project requirementC.project charterD.product specification

()describees,indetail,the project's deliverables and the work required to create those deliverables. A.Product scope description B.Project objectivesC.Produce specificationD.The project scope statement

In project management, a ( ) is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。A.scheduleB.activityC.PlanD.contractor

( ) describes,in detail,the project’s deliverables and the work required to create those deliverables. A.Product scope description B.Project objectives C.Stakeholder Analysis D.The project scope statement

The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.A.Project scope statementB.Work packageC.WBSD.Project scope plan

The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter B.project scope goal C.project budget D.project scope statement

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resourceB.individual work loadC.work milestoneD.work package

In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events. A、scheduleB、WBSC、SOWD、charter

()describes, in detail, the project’s deliverables and the work required to create those deliverables.A、Product scope descriptionB、Project objectivesC、Stakeholder AnalysisD、The project scope statement

The () describes, in detail, the project's deliverables and the work required to create those deliverables.A、project scope statementB、project requirementC、project charterD、product specification

单选题In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.AscheduleBactivityCplanDcontractor

单选题The()describes, in detail, the project's deliverables and the work required to create those deliverables.Aproject scope statementBproject requirementCproject charterDproduct specification

单选题The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.Awork performance informationBscope statementCchangerequestsDprocess analysis

单选题The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.AsubdividingBassessingCplanningDintegrating

单选题Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()AindependentresourceBindividualworkloadCworkmilestoneDworkpackage