Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()A.Scope PlanningB.Scope VerificationC.Scope Change ControlD.Scope Definition

Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()

A.Scope Planning
B.Scope Verification
C.Scope Change Control
D.Scope Definition

参考解析

解析:在以下项目范围管理几个过程中,(74)涉及将主要项目可交付成果细分成更小、更容易管理的组件单元。A.范围规划B.范围确认C.范围变更控制D.范围定义

相关考题:

Which of the following is not a scope management process?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

In which of the following scope management processes is the scope management plan prepared?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

The project charter is prepared in which scope management process?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

In which of the following scope management processes are subject matter experts used?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level() A.independentresourceB.individualworkloadC.workmilestoneD.workpackage

140 In which of the following scope management processes are subject matter experts used? A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

143 In which of the following scope management processes is the scope management plan prepared?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

● The inputs of developing project management plan do not include (72).(72)A. project charterB. stakeholder management strategyC. project scope statementD. outputs from planning processes

● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.(75)A.independent resourceB.individual work loadC.work milestoneD.work package

The inputs of developing project management plan do not include (72) .A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes

The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes

In project management and systems engineering,()is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.A.RBSB.PBSC.GBSD.WBS

● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)(74)A. Scope PlanningB. Scope VerificationC. Scope Change ControlD. Scope Definition

In project time management processes,( )involves identifying and documenting the relationships between project activities.A.activity definitionB.activity sequencingC.schedule controlD.Schedule development

Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.A.cost management planB.risk management planC.scope management planD.management schedule

()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.A.The project charterB.The project scope statementC.The WBS dictionaryD.The activity list

Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.A.cost management planB.risk managementC.scope management planD.management schedule

Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.A.cost management plan B.risk managementC.scope management planD.management schedule

The inputs of developing project management plan do not include()A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes

()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopEB:Project stakeholder managementC:Project scope managementD:Project cost management

The inputs of developing project management plan do not include (). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes

()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopEB. Project stakeholder managementC. Project scope managementD. Project cost management

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level. A.independent resource B.individual work loaD. C.work milestone D.work package

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resourceB.individual work loadC.work milestoneD.work package

The inputs of developing project management plan do not include()A、project charterB、stakeholder management strategyC、project scope statementD、outputs from planning processes

单选题Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()AindependentresourceBindividualworkloadCworkmilestoneDworkpackage

单选题The inputs of developing project management plan do not include()Aproject charterBstakeholder management strategyCproject scope statementDoutputs from planning processes