单选题A technical specialist has a requirement to implement a 4-way POWER5 server with a small Web server partition and a high performance database server partition. The Web server provides a client front-end to the database server. The most important concerns are speed of communication between the Web server and the database and I/O speed of the database. Which of the following virtualization features would be most appropriate?()AVirtual SCSIBVirtual EthernetCVirtual I/O ServerDMicro-Partitioning

单选题
A technical specialist has a requirement to implement a 4-way POWER5 server with a small Web server partition and a high performance database server partition. The Web server provides a client front-end to the database server. The most important concerns are speed of communication between the Web server and the database and I/O speed of the database. Which of the following virtualization features would be most appropriate?()
A

Virtual SCSI

B

Virtual Ethernet

C

Virtual I/O Server

D

Micro-Partitioning


参考解析

解析: 暂无解析

相关考题:

A technical requirement has which of the following characteristics:A.easy to understandB.a communication tool between the user and the design teamC.written in non-technical languageD.developed in cooperation with the userE.typically describe physical dimensions and performance requirements

96 A technical requirement has which of the following characteristics:A. easy to understandB. a communication tool between the user and the design teamC. written in non-technical languageD. developed in cooperation with the userE. typically describe physical dimensions and performance requirements

● A technical requirement has which of the following characteristics:A easy to understandB a communication tool between the user and the design teamC written in non-technical languageD developed in cooperation with the userE typically describe physical dimensions and performance requirements

A requirement is simply a statement of what the system must do or what characteristics it needs to have. Requirements evolve from broad statements of overall (71)from the system to detailed statements of the business capabilities that a system should support to detailed technical statements of the way in which the capabilities will be implemented in the new system. (72)focus on describing how to create the software product that will be produced from the project Nonfunctional requirements are primarily used in the design phase when decisions are made about the user interface, the hardware and software, and the system's underlying architecture. The system's physical and technical environments would be considered (73). The speed, capacity, and reliability of the system belong to (74).(75)describes that who has authorized access to the system under what circumstances.(74)应选?A.security requirementB.performance requirementC.technical requirementD.information requirement

The storage specialist has designed a very complex solution with the customer, and needs toverify that all associated equipment will work as expected. Which of the following is designed tohelp lower support cost and improve customer satisfaction?()A、ATScon MonitorB、Technical and Delivery AssessmentC、System Storage Interoperations CenterD、Standalone Solutions Configuration Tool

A technical specialist has a requirement to implement a 4-way POWER5 server with a small Web server partition and a high performance database server partition. The Web server provides a client front-end to the database server. The most important concerns are speed of communication between the Web server and the database and I/O speed of the database. Which of the following virtualization features would be most appropriate?()A、Virtual SCSIB、Virtual EthernetC、Virtual I/O ServerD、Micro-Partitioning

A financial industry customer will consolidate their Intel-based servers to a p5-550 running AIX, and needs experienced technical services.  What information should the account executive provide to the customer to assure them that the technical specialist has the required experience?()A、The technical specialist has supported multiple Cluster 1350 environments. References will be provided.B、The technical specialist is Linux-certified by two industry groups. Certificate copies will be provided.C、The technical specialist has worked on multiple UNIX consolidation projects.  References will be provided.D、The technical specialist has worked on Linux consolidation efforts.  References will be provided.

The pSeries technical specialist has been invited to a briefing on the latest POWER technology as a representative of their team.  What should the specialist offer to do upon return from class in order to best prepare the rest of the team for the introduction of the new technology?()A、Archive the materials in the team’s library.B、Act as the sole technical resource for the team.C、Summarize the information and make it available to the team.D、Evaluate the class and recommend attendance to other team members.

A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them.  Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()A、The technical support specialist has completed a UNIX course at college.B、The technical specialist has supported several similar projects and has earned an IBM AIX certification.C、The technical support specialist’s company sells $3M of UNIX computer systems every year.D、The technical support specialist has sold and installed at least a dozen Apple and iSeries systems with POWER processors.

A customer has two locations that host their pSeries servers.  Traffic is being routed through the public Internet.  The customer needs to exchange confidential financial data between the servers.  Which of the following solutions should the pSeries technical specialist propose to the customer to secure the data?()A、A DCE domainB、A Kerberos domainC、A PPP tunnel between the serversD、An IPSEC tunnel between the servers

The workload requirement for a Web server running in Micro-Partitioned p5-550 has increased 300 percent over the past six months. The initial partition definitions assigned 0.5 processing units and one virtual processor to the Web server partition. Three months previously, an additional 0.5 CPU was added to the Web server partition. When the technical specialist attempted to allocate a further 0.5 CPU to this partition, no additional performance was achieved. Which of the following actions would most likely resolve the problem?()A、Add another virtual Ethernet.B、Change the partition to be uncapped.C、Change the number of virtual processors to 2.D、Increase the amount of memory assigned to the partition by 300 percent.

The client team tends to bring the pSeries technical specialist in very late in the process.  This has caused several problems where the specialist has had to correct some misunderstandings about the technology.  The specialist is getting very frustrated and would like to avoid these misunderstandings in future. What would be the most appropriate way to handle this?()A、Refuse to work with the account team unless they are brought in right at the beginning.B、Talk to the account team and ask them to bring them in earlier so that they can better understand the account.C、Explain the situation to the customer and ask them to talk to the account team about bringing them in earlier.D、Explain the situation to the sales manager and ask him to talk to the account team about bringing them in earlier.

A customer has just obtained a second data center through the acquisition of a competitor.   The IT Director is now seeking to merge,integrate,and rebalance systems across the two data centers over thenext two years.   They have just deployed a high-speed point-to-point circuit between the facilities. The IT Director would like a system that could backup their AIX and Win2K servers and electronically vault the data between sites as part of their Disaster Recovery Plan.   What product should the pSeries technical specialist recommend for this requirement?()A、CSMB、TSMC、NIMD、Sysback

The pSeries technical specialist has been asked to verify a solution that has six servers connecting to a 7316-TF3 rack-mounted flat-panel console.   Each server will connect into the 4202 Keyboard/Video/Mouse (LCM Switch).   What is the minimum number of KVM Conversion Cable Options (FC 4268) required to complete this installation?()A、1B、2C、6D、8

The pSeries technical specialist is concerned that the installed inventory for a p670 does not match what the customer says is installed.  The specialist discovers that the customer has never updated their VPD.  Which of the following HMC applications is used to gather the current VPD information?()A、Service ProcessorB、Service DirectorC、Inventory Scout ServicesD、Service Focal Point

A customer has an IBM System Storage DS8100 and wants to reach the highest possible throughput in the back-end for a storage-pool-striped volume out of an extent pool with 8 ranks.  Over how many device adapter pairs should a technical specialist spread the workload()A、2B、4C、6D、8

A company has recently placed an order for a POWER4+ p650 server.   Their facilities manager has approached the pSeries technical specialist to gather information on the correct power receptacle for thenew server.   They have requested a picture of the power cord plug to show to their electrician.  Where would the pSeries technical specialist find the required information?()A、Sales ManualB、Announcement LetterC、POWER4+ p650 Specification SheetD、Site and Hardware Planning Information Manual

An IBM technician specialist has a prospective customer who is excited about eX5 and is working on configuration for a very large complex opportunity. During the engagement the customer has changed the design several times and has significantly increased the scope. The customers recently selected a Business Partner who has been involved in the last few design changes. What steps should the IBM technician specialist take to make sure the customer is satisfied with the solution?()A、Turn over current design to Techline to create configurationsB、Perform knowledge transfer of design requirements to Business partner then disengageC、Work with Business Partner to engage Techline to assist with configuration and request technical and Delivery Assessment (TDA)D、Work with business partner to engage Techline to create configurations

Companycom has a p5 595 running 12 LPARs. They are interested in high bandwidth, secure communication between two of the LPARs within the p5 595 server. They do not have any unused Ethernet adapters. Which of the following recommendations will best meet this requirement?()A、Utilize the integrated 10/100/1000 network interfaceB、Implement Virtual Ethernet to enable inter-partition communicationC、Implement shared Ethernet with the Ethernet adapters utilized in the other LPARsD、Implement a Point to Point protocol serial communication between the p5 595 serial ports

单选题A customer has a requirement to build a 4 node cluster. Disk heartbeating will be used as the non-IP network.What is the maximum number of disk heartbeat point-to-point links one would need to implement in order toachieve the highest level of availability?()A4B6C8D12

单选题The pSeries technical specialist has been asked to verify a solution that has six servers connecting to a 7316-TF3 rack-mounted flat-panel console.   Each server will connect into the 4202 Keyboard/Video/Mouse (LCM Switch).   What is the minimum number of KVM Conversion Cable Options (FC 4268) required to complete this installation?()A1B2C6D8

单选题The pSeries technical specialist of a Premier Tier 1 Business Partner has been working on a design for a four LPAR p5-570 Express solution.  The specialist has received conflicting information regarding sharing the IDE DVD-RAM drive between different LPARs.  Who should the technical specialist contact to gain a definitive answer?()AIBM BPSOBIBM PartnerlineCIBM DistributorDIBM Supportline

单选题A pSeries technical specialist has just returned from an internal course for implementing Micro-Partitioning on the POWER5 range of servers.  There were many handouts from the course.  To ensure the rapid transfer of the newly acquired skill, what should the technical specialist do?()AMake copies of the course material and deliver the course in full to the technical team.BMake copies of the course material and hand them out to the technical team for them to read.CBecome the Micro-Partitioning expert within the organization and act as the sole knowledge base.DMake copies of the course material and prepare a concise overview of the course to deliver to the technical team.

单选题A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them.  Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()AThe technical support specialist has completed a UNIX course at college.BThe technical specialist has supported several similar projects and has earned an IBM AIX certification.CThe technical support specialist’s company sells $3M of UNIX computer systems every year.DThe technical support specialist has sold and installed at least a dozen Apple and iSeries systems with POWER processors.

单选题A university researcher needs a large server with high numeric computing capacity to do computational fluid dynamics calculations.  The pSeries technical specialist has a recent pSeries and RS/6000 Performance Report.  Which of the following tables should be consulted to advise the customer concerning relative performance of various models?()ArPerfBROLTPCSPECfpDSPECint

单选题A customer has requested a proposal for a p5-520 with AIX 5.2 and Sysback.  There are no plans to run LPARs or Micro-Partitions on the p5-520 in the near future.  The customer has asked the pSeries technical specialist to recommend anything else that may be needed.  Which of the following should be recommended in this situation?()AHMCBDVD-ROMCTape driveDNetwork switch

单选题A financial industry customer will consolidate their Intel-based servers to a p5-550 running AIX, and needs experienced technical services.  What information should the account executive provide to the customer to assure them that the technical specialist has the required experience?()AThe technical specialist has supported multiple Cluster 1350 environments. References will be provided.BThe technical specialist is Linux-certified by two industry groups. Certificate copies will be provided.CThe technical specialist has worked on multiple UNIX consolidation projects.  References will be provided.DThe technical specialist has worked on Linux consolidation efforts.  References will be provided.