The() defines the phases that connect the beginning of a project to its end.A、scheduleB、project life cycleC、temporaryD、milestone
The() defines the phases that connect the beginning of a project to its end.
- A、schedule
- B、project life cycle
- C、temporary
- D、milestone
相关考题:
The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.A . budget, scheduleB . quality requirements, scheduleC . size, type of industryD . nature, sizeE . project manager, sponsor
The time necessary to complete a project is called the _______ of a project.A.Implementation TimeB.Life CycleC.Operation TimeD.Critical PathE.Completion Phase
Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.APreliminary planning, detail planning, closeoutBImplementation, reporting, terminationCDevelopment, implementation, terminationDExecution, reporting, finishingEImplementation, termination, post-audit review
The sequential steps that define the process for successfully completing a project is:A.Implementation PlanB.a life cycleC.Development PlanD.a critical pathE.Management Plan
A negative cost variance and positive schedule variance means:A The project is under budget and ahead of scheduleB The project is over budget and behind scheduleC The project is over budget and ahead of scheduleD The project will be overrun but ahead of schedule at completion
115 The sequential steps that define the process for successfully completing a project is: A. Implementation PlanB. a life cycleC. Development PlanD. a critical pathE. Management Plan
66 The time necessary to complete a project is called the _______ of a project.A. Implementation TimeB. Life CycleC. Operation TimeD. Critical PathE. Completion Phase
69 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.A. budget, scheduleB. quality requirements, scheduleC. size, type of industryD. nature, sizeE. project manager, sponsor
● The time necessary to complete a project is called the _______ of a project.A Implementation TimeB Life CycleC Operation TimeD Critical PathE Completion Phase
● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.A Preliminary planning, detail planning, closeoutB Implementation, reporting, terminationC Development, implementation, terminationD Execution, reporting, finishingE Implementation, termination, post-audit review
● The sequential steps that define the process for successfully completing a project is:A Implementation PlanB a life cycleC Development PlanD a critical pathE Management Plan
means that every project has a definite beginning and a definite end.A.Project phaseB.UniqueC.TemporaryD.Closure
The(67)defines the phases that connect the beginning of a project to its end.A.scheduleB.project life cycleC.temporaryD.milestone
根据材料回答3~4题: A project life cycle is a collection of generally sequential project(73)whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic(74)for managing the project,regardless ofthe specific work involve D. A.phases B.processes C.segments D.pieces
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
The (71) defines the phases that connect the beginning of a project to its end.A.milestoneB.scheduleC.temporaryD.project life cycle
In project management, a ( ) is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。A.scheduleB.activityC.PlanD.contractor
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )A.devclopmentB.conceptC.system analysisD.implementation
There are four phases in the life cycle of a project:start,plan,execute and( ).A.implementB.performanceC.endD.excute
The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).A.developmentB.conceptC.system analysisD.implementation
The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ). A.development B.concept C.system analysis D.implementation
A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project. A.phases B.processes C.segments D.pieces
()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A、gantt chartB、project histogramC、milestone chartD、project flowchart
()means that every project has a definite beginning and a definite end.A、Project phaseB、UniqueC、TemporaryD、Closure
()means that every project has a definite beginning and a definite end.A、ProjectphaseB、UniqueC、TemporaryD、Closure
单选题The() defines the phases that connect the beginning of a project to its end.AscheduleBproject life cycleCtemporaryDmilestone