The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ). A.development B.concept C.system analysis D.implementation

The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ).

A.development
B.concept
C.system analysis
D.implementation

参考解析

解析:

相关考题:

Which of the following are included in the Acquisition phase(s) of the project life cycle.A . concept and developmentB . development and planningC . execution and phase-outD . planning and implementationE . concept and planning

Feasibility studies occur in which life cycle phase (s)?A.ConceptualB.Conceptual or DevelopmentC.ExecutionD.Preliminary planningE.any life cycle phase

The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.A.ConceptualB.Development.C.ExecutionD.FinishE.All of the above.

QUEST . Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A . 5%B . 10%C . 15%D . 25%E . 50%

Typically, during which phase in a project life cycle are most of the project expenses incurred.A . Concept phaseB . Development of design phaseC . Execution phase.D . Termination phase.E . None of the above

During which phase of the project life cycle is the amount at stake lowest?A conceptB developmentC executionD conclusionE C and D

67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. ConceptualB. Development.C. ExecutionD. FinishE. All of the above

95 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A. 5%B. 10%C. 15%D. 25%E. 50%

141 Feasibility studies occur in which life cycle phase (s)?A. ConceptualB. Conceptual or DevelopmentC. ExecutionD. Preliminary planningE. any life cycle phase

194 During which phase of the project life cycle is the amount at stake lowest?A. conceptB. developmentC. executionD. conclusionE. C and D

6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phaseB Development of design phaseC. Execution phase.D. Termination phase.E. None of the above

88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phaseB. Development of design phaseC. Execution phase.D. Termination phase.E. None of the above

82 Which of the following are included in the Acquisition phase(s) of the project life cycle.A. concept and developmentB. development and planningC. execution and phase-outD. planning and implementationE. concept and planning

● Feasibility studies occur in which life cycle phase (s)?A ConceptualB Conceptual or DevelopmentC ExecutionD Preliminary planningE any life cycle phase

● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A 5%B 10%C 15%D 25%E 50%

● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.A ConceptualB Development.C ExecutionD FinishE All of the above.

A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.A.phasesB.processesC.segmentsD.pieces

根据材料回答3~4题: A project life cycle is a collection of generally sequential project(73)whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic(74)for managing the project,regardless ofthe specific work involve D. A.phases B.processes C.segments D.pieces

The (71) defines the phases that connect the beginning of a project to its end.A.milestoneB.scheduleC.temporaryD.project life cycle

The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycleIt is().A.developmentB.conceptC.system analysisD.implementation

Which of the following statements is correct?A.The definition phase results in the Software Requirements Specification.B.Testing is optional in software life cycle.C.CASE tools can only aid in the design phase of a software life cycle.D.A change during a later phase does not require the documentation of all earlier phases to be updated.

A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic for managing the project, regardless of the specific work involved.A.phasesB.processesC.segmentsD. pieces

A project life cycle is a collection of generally sequential project whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic () for managing the project, regardless of the specific work involved.A. planB. fractionC. mainD.framework

The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )A.devclopmentB.conceptC.system analysisD.implementation

There are four phases in the life cycle of a project:start,plan,execute and( ).A.implementB.performanceC.endD.excute

The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).A.developmentB.conceptC.system analysisD.implementation

A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project. A.phases B.processes C.segments D.pieces