● The sequential steps that define the process for successfully completing a project is:A Implementation PlanB a life cycleC Development PlanD a critical pathE Management Plan

● The sequential steps that define the process for successfully completing a project is:

A Implementation Plan

B a life cycle

C Development Plan

D a critical path

E Management Plan


相关考题:

The time necessary to complete a project is called the _______ of a project.A.Implementation TimeB.Life CycleC.Operation TimeD.Critical PathE.Completion Phase

The sequential steps that define the process for successfully completing a project is:A.Implementation PlanB.a life cycleC.Development PlanD.a critical pathE.Management Plan

115 The sequential steps that define the process for successfully completing a project is: A. Implementation PlanB. a life cycleC. Development PlanD. a critical pathE. Management Plan

66 The time necessary to complete a project is called the _______ of a project.A. Implementation TimeB. Life CycleC. Operation TimeD. Critical PathE. Completion Phase

● The time necessary to complete a project is called the _______ of a project.A Implementation TimeB Life CycleC Operation TimeD Critical PathE Completion Phase

● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.A Preliminary planning, detail planning, closeoutB Implementation, reporting, terminationC Development, implementation, terminationD Execution, reporting, finishingE Implementation, termination, post-audit review

● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)(75)A. Project Scope StatementB. Project Management PlanC. ForecastsD. Project Charter

The(70)provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.contractC.project human resource planD.project charter

The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter

The( )provides the project manager with the authority to apply organizational resources to project activities。A.project management planB.project charterC.project human resource planD.project stakeholders

●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).(73)A. project management planB. project baselineC. risk response planD. risk baseline

● The development process in the software (74) involves four phases: analysis,design,implementation, and testing.(74) A. maintenanceB. life cycleC. programmingD. upgrading

The communication management plandetermines the information and communications needs of the stakeholders. In thefollowing statements related to communication management plan, (73) is false.A.The communication management plan is contained in, or is a subsidiary plan of, the project management planB.The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the projectC.The communication management plan organize and summarize the information gathered, and present the results of any analysis as compared to the performance measurement baselineD.The communication management plan can include guidelines for project status meetings, project team meetings, e-meetings, and e-mails

The (73) provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.project charterC.project human resource planD.project stakeholders

The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).A.Project Scope StatementB.Project Management PlanC.ForecastsD.Project Charter

Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.A.cost management planB.risk managementC.scope management planD.management schedule

A project life cycle is a collection of generally sequential project whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic () for managing the project, regardless of the specific work involved.A. planB. fractionC. mainD.framework

The Develop Project Management Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ( )A. Project Scope StatementB.Project Management PlanC.ForecastsD.Project Charter

Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element A.cost management planB.risk management planC.soope management planD.management schedule

Managing risk and documenting them is very important in project planning process.You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the(73) .A.project management planB.project baselineC.riskresponse planD.risk baseline

The development process in the software______involves four phases:analysis,design,implementation,and testing.A.maintenanceB.1ife cycleC.programmingD.upgrading

Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project

A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.taskB.workC.sequenceD.activity

The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、project charter

The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、projectcharter

Which design phase service component includes the development and documentation of the test case or cases used to verify that a deployed infrastructure meets operational, functional, and interface requirements? Select exactly 1 answer(s) from the following:()。A、Implementation PlanB、Business PlanC、Staging PlanD、Detailed Design DevelopmentE、Systems Acceptance Test Plan Development

A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved.空白(2)处应选择()A、planB、fractionC、mainD、framework