()means that every project has a definite beginning and a definite end.A、Project phaseB、UniqueC、TemporaryD、Closure
()means that every project has a definite beginning and a definite end.
- A、Project phase
- B、Unique
- C、Temporary
- D、Closure
相关考题:
A program is characterized as:A.a grouping or related tasks lasting one year or less.B.a unique undertaking having a definite time period.C.a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.D.a project with a cost over $ million.E.None of the above.
Documented work authorization provide:A.a means of effective internal coordination of the project's activities.B.an audit trail of all work authorized from project initiation to completion.C.a means for communication of work activity between the project manager and the performing activities.D.All of the aboveE.A and B only.
Typically, during which phase in a project life cycle are most of the project expenses incurred.A . Concept phaseB . Development of design phaseC . Execution phase.D . Termination phase.E . None of the above
Of the following, who has the ultimate responsibility for meeting project quality objectives?A . Project EngineerB . Project ManagerC . Functional ManagerD . Quality Assurance ManagerE . Project Owner
Which of the following tools and techniques can be used to collect information for the project closure reports?A Customer SurveysB BrainstormingC Document and Performance AnalysisD Lessons LearnedE All of the above
The following reports are normally developed during the project closure phase?A Communications Management Plan and Lessons LearnedB Records Archive, Closure Report, lessons learned Formal Acceptance ReportC Records Archive, Closure Report, Specifications DocumentD Communications Management Plan and Closure reportE None of the above
A negative cost variance and positive schedule variance means:A The project is under budget and ahead of scheduleB The project is over budget and behind scheduleC The project is over budget and ahead of scheduleD The project will be overrun but ahead of schedule at completion
For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?A project office memoB project office directiveC project team meetingD formal reportE counseling sessions
112 Of the following, who has the ultimate responsibility for meeting project quality objectives?A. Project EngineerB. Project ManagerC. Functional ManagerD. Quality Assurance ManagerE. Project Owner
171 Documented work authorization provide:A. a means of effective internal coordination of the project's activities.B. an audit trail of all work authorized from project initiation to completionC.a means for communication of work activity between the project manager and the performing activities.D. All of the aboveE. A and B only
200 A program is characterized as:A. a grouping or related tasks lasting one year or less.B. a unique undertaking having a definite time period.C. a grouping of similar projects having no definite end that supports the product(s) from cradle to grave. D. a project with a cost over $1 million.E. None of the above
6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phaseB Development of design phaseC. Execution phase.D. Termination phase.E. None of the above
88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phaseB. Development of design phaseC. Execution phase.D. Termination phase.E. None of the above
96 A negative cost variance and positive schedule variance means:A. The project is under budget and ahead of scheduleB. The project is over budget and behind scheduleC. The project is over budget and ahead of scheduleD. The project will be overrun but ahead of schedule at completion
97 The following reports are normally developed during the project closure phase?A. Communications Management Plan and Lessons LearnedB. Records Archive, Closure Report, lessons learned Formal Acceptance ReportC. Records Archive, Closure Report, Specifications DocumentD. Communications Management Plan and Closure reportE. None of the above
● The use of the project reports:A are not necessary on small projectsB provides a means whereby various levels of authority can judge project performanceC provides insight into project areas and the effectiveness of the control systemsD All of the aboveE B and C
means that every project has a definite beginning and a definite end.A.Project phaseB.UniqueC.TemporaryD.Closure
The(67)defines the phases that connect the beginning of a project to its end.A.scheduleB.project life cycleC.temporaryD.milestone
The (71) defines the phases that connect the beginning of a project to its end.A.milestoneB.scheduleC.temporaryD.project life cycle
The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )A.devclopmentB.conceptC.system analysisD.implementation
The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).A.developmentB.conceptC.system analysisD.implementation
()means that every project has a definite beginning and a definite end.A、ProjectphaseB、UniqueC、TemporaryD、Closure
The() defines the phases that connect the beginning of a project to its end.A、scheduleB、project life cycleC、temporaryD、milestone
Who is responsible for authorizing closure of the project?()A、Project ManagerB、StakeholderC、CustomerD、Executive Sponsor
单选题Who is responsible for authorizing closure of the project?()AProject ManagerBStakeholderCCustomerDExecutive Sponsor
单选题()means that every project has a definite beginning and a definite end.AProject phaseBUniqueCTemporaryDClosure
单选题()means that every project has a definite beginning and a definite end.AProjectphaseBUniqueCTemporaryDClosure