单选题In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?()AThe safety valve escape piping should be disconnected from the valve body and a blank insertedBThe boiler vent valves should be openedCAll hand-hole/manhole covers should be tightened up as much as possible to preclude any leaksDAll of the above

单选题
In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?()
A

The safety valve escape piping should be disconnected from the valve body and a blank inserted

B

The boiler vent valves should be opened

C

All hand-hole/manhole covers should be tightened up as much as possible to preclude any leaks

D

All of the above


参考解析

解析: 暂无解析

相关考题:

The correct procedure for giving an auxiliary boiler a bottom blow, is to begin .A.when the boiler has been secured long enough for most solids to settleB.when the boiler has been cooled to ambient temperatureC.only after raising the water level to within 0.5 inch of the high water cutout onlyD.after bypassing the low pressure

If the feed pump for an auxiliary boiler fails to deliver the feed water to the boiler, the cause may be ______.A.high steam pressure in the boilerB.abnormally high feed-water temperatureC.abnormally high boiler water temperatureD.steam demand exceeding feed pump capacity

The boiler water alkalinity in a coil-type auxiliary boiler should be maintained at the pH recommended by the boiler manufacturer to______.A.precipitate(使沉淀) silica (硅石)from solutionB.reduce corrosion in the heating coilC.prevent clogging and erosion in the coilD.maintain zero water hardness

单选题The most common cause of scale formation in an auxiliary boiler is ()Aconcentrations of calcium sulfate in the boiler waterBfuel oil in the feed waterCimproper treatment of the feed water with calcium sulfateDexcessive feed water alkalinity

单选题The water level of an exhaust gas boiler which is independent of the auxiliary boiler and just as the extra heating surface of it ()Awill be modulated in proportionBwill be modulated in proportion and integralCwill be modulated in proportion and differentialDwill not be modulated at all

单选题What is NOT a function of the steam drum of a marine water-tube boiler().AReceives saturated steam from the generating tubesBServes as a reservoir of boiler feed waterCHolds internal fittings for separation of moisture from steamDCollects steam exhausted from the turbines

单选题The purpose of the safety relief valves installed on an auxiliary boiler is to ().Arelieve excess fuel oil pressure during the “off” fire cycleBadmit water to the dry pipeCthrottle the forced draft fan output for proper combustionDreduce excess steam pressure in the boiler

单选题In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?()AThe safety valve escape piping should be disconnected from the valve body and a blank insertedBThe boiler vent valves should be openedCAll hand-hole/manhole covers should be tightened up as much as possible to preclude any leaksDAll of the above

单选题In the event of a flame failure in an auxiliary water-tube boiler, you must()Arelight the boiler immediately to prevent loss of steam pressureBrelight the fire off the brickwork as the bricks are cherry redCpurge the furnace of any combustible gases before attempting to relight the fireDspeed up the feed pump to prevent dry firing when the burner flame is reestablished

单选题The rate of heat transfer in a water-tube auxiliary boiler can be increased by ().Aoperating the boiler at less than normal water levelBinstalling fins on the firesides of water-tubesCincreasing the amount of excess air to the burnersDtreating the boiler water with chemical oxygen scavengers

单选题In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?()AThe safety valve escape piping should be disconnected from the valve body and a blank insertedBThe boiler vent valves should be openedCAll handhole/manhole covers should be tightened up as much as possible to preclude any leaksDAll of the above

单选题In an auxiliary boiler steam and water system, the highest pressure will be in the ().Asteam stop valveBdry pipeCfeedwater systemDgenerating tubes

单选题The correct procedure for giving an auxiliary boiler a bottom blow, is to begin()Awhen the boiler has been secured long enough for most solids to settleBwhen the boiler has been cooled to ambient temperatureConly after raising the water level to within 0~5 inch of the high water cutout onlyDafter bypassing the low pressure

单选题Bottom blow valves are installed on auxiliary water-tube boilers to ()Aremove suspended and precipitated solids from the boiler waterBcompletely drain the boiler in an emergency situationCprevent hardened scale deposits in the water drumDremove floating impurities from the oily water surface

单选题A distorted furnace in a fire-tube auxiliary boiler may be the result of ()Afiring for extended periods in the low fire modeBoverheating, due to waterside depositsCvarying the water level above the crown sheetDcarrying excessive alkalinity in the boiler water

单选题The water in an auxiliary boiler should be tested daily for ().Adissolved oxygenBchloridesCsludgeDdissolved nitrogen

单选题The fuel supply system to an automatic auxiliary boiler, will be automatically shutdown if the boiler ()Asalinity is abnormally highBsteam demand is too highCwater level is abnormally lowDfeedwater flow is low

单选题The water in an auxiliary boiler should be chemically tested daily for alkalinity and()Asoap hardnessBnitrog encontentCchloride contentDdissolved CO2

单选题The fuel oil supply system to an automatic auxiliary boiler, will automatically shutdown if the boiler ()Asteam demand is highBsalinity is highCsafety valve simmersDburner flame is extinguished

单选题A () boiler is an auxiliary boiler sometimes included in a steamships installation for supplying steam to auxiliaries in port.AmonkeyBdonkeyCwaste heatDmain

单选题The boiler water alkalinity in a coil-type auxiliary boiler should be maintained at the pH recommended by the boiler manufacturer to()Aprecipitate silica from solutionBreduce corrosion in the heating coilCprevent clogging and erosion in the coilDmaintain zero water hardness

单选题The water in an auxiliary boiler should be tested for chloride content to determine ().Atotal dissolved solidsBsalt contaminationCwater hardnessDchlorine contamination

单选题The amount of chloride content in the water of an auxiliary boiler can be reduced by()Aadding hydrazineBblowing down the boilerCadding phenolphthaleinDadding a sulfite chloride scavenger

单选题Excessive alkalinity of the water in an auxiliary boiler can cause ().Acaustic embrittlement of the boiler metalBacidic corrosion of the boiler metalChard scale deposits on the boiler tubesDetching of the heat exchange surfaces

单选题Bottom blow valves are installed on auxiliary water-tube boilers to ()Acompletely drain the boiler in an emergencyBprevent sludge from forming in the drumCremove floating impurities from the boiler water surfaceDremove settled solids from the water drum

单选题If the feed pump for an auxiliary boiler fails to deliver the feed water to the boiler, the cause maybe ().Ahigh steam pressure in the boilerBabnormally high feed water temperatureCabnormally high boiler water temperatureDsteam demand exceeding feed pump capacity

单选题Before an auxiliary boiler is shutdown for an extended period of time, the water in the boiler should have a pH value of ().A10B7C4D1

单选题The water in an operating auxiliary boiler should be tested for alkalinity and chloride content each().AhourBdayCweekDmonth