单选题Bottom blow valves are installed on auxiliary water-tube boilers to ()Aremove suspended and precipitated solids from the boiler waterBcompletely drain the boiler in an emergency situationCprevent hardened scale deposits in the water drumDremove floating impurities from the oily water surface

单选题
Bottom blow valves are installed on auxiliary water-tube boilers to ()
A

remove suspended and precipitated solids from the boiler water

B

completely drain the boiler in an emergency situation

C

prevent hardened scale deposits in the water drum

D

remove floating impurities from the oily water surface


参考解析

解析: 暂无解析

相关考题:

The correct procedure for giving an auxiliary boiler a bottom blow, is to begin .A.when the boiler has been secured long enough for most solids to settleB.when the boiler has been cooled to ambient temperatureC.only after raising the water level to within 0.5 inch of the high water cutout onlyD.after bypassing the low pressure

The system of valves and cargo lines in the bottom piping network of a tanker that connects one section of cargo tanks to another section is called a ______.A.come-alongB.crossoverC.manifoldD.runaround

When installing a server in a rack, which of the following locations describes where in the rack a server should be installed?()A、On the very bottom U of the rack, with the UPS above the serverB、In the middle of the rack to help balance the rackC、Closest to the bottom of the rack, above heavier equipmentD、On the very top U of the rack, with the UPS directly below it

单选题The concentration of total dissolved solids in the water of an auxiliary boiler can increase as a result of ().Aseawater contaminationBfrequent surface blowsCdissolved oxygen deaerationDfrequent bottom blows

单选题The purpose of the safety relief valves installed on an auxiliary boiler is to ().Arelieve excess fuel oil pressure during the “off” fire cycleBadmit water to the dry pipeCthrottle the forced draft fan output for proper combustionDreduce excess steam pressure in the boiler

单选题Blow-off of the relief valves of the main cylinders during operation indicates ().Athe cylinder cover is crackedBthe injector holes is cloggedCthe cams are not properly setDfuel pump is leaking

单选题In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?()AThe safety valve escape piping should be disconnected from the valve body and a blank insertedBThe boiler vent valves should be openedCAll hand-hole/manhole covers should be tightened up as much as possible to preclude any leaksDAll of the above

单选题In the event of a flame failure in an auxiliary water-tube boiler, you must()Arelight the boiler immediately to prevent loss of steam pressureBrelight the fire off the brickwork as the bricks are cherry redCpurge the furnace of any combustible gases before attempting to relight the fireDspeed up the feed pump to prevent dry firing when the burner flame is reestablished

单选题The rate of heat transfer in a water-tube auxiliary boiler can be increased by ().Aoperating the boiler at less than normal water levelBinstalling fins on the firesides of water-tubesCincreasing the amount of excess air to the burnersDtreating the boiler water with chemical oxygen scavengers

单选题In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?()AThe safety valve escape piping should be disconnected from the valve body and a blank insertedBThe boiler vent valves should be openedCAll handhole/manhole covers should be tightened up as much as possible to preclude any leaksDAll of the above

单选题The correct procedure for giving an auxiliary boiler a bottom blow, is to begin()Awhen the boiler has been secured long enough for most solids to settleBwhen the boiler has been cooled to ambient temperatureConly after raising the water level to within 0~5 inch of the high water cutout onlyDafter bypassing the low pressure

单选题The donkey boiler may be given a bottom blow ()Ato raise water levelBonly while making steamCto remove scumDwhen fire are secured

单选题Which of the following items isn’t belonging to Docking survey?()AExamination of the shell including bottom, side and bow platingBExamination of sea suctions, overboard discharging valves and sea chestsCLoad testing of lifeboat launching devicesDPoker gauge of propeller shaft taken

单选题Blow-off of the relief valves of the engines cylinders may be caused by ().Atoo low leadBwater in fuelCtoo tight springDleakage

单选题Excessive valve lash in an auxiliary diesel engine will cause the valves to open()Alater and close soonerBsooner and close laterCsooner and close soonerDlater and close later

单选题The clearance volume for a single stage compressor is defined as the space created between the ().Atop of the piston and bottom side of head, with the piston at BDCBpiston and head, including the space around the piston to the top of the upper ring and under the valves, with the piston at TDCCbottom of the piston and bottom side of the head at TDC, regardless of upper ring location and valve placementDtop of the piston and bottom side of the head at TDC as compared to that which exists between the top of the piston and bottom side of head at BDC

单选题Which of the following actions should normally be taken during each watch when the auxiliary boilers is in operation?()Aclean the flame scanner photocell windowBInspect and clean all solenoid valvesClift the safety valves by handDInspect for oil or water leaks

单选题Thermostatic steam pressure reducing valves are used in the fuel oil service system to control the()Adouble bottom fuel oil tank temperatureBheater supply steam flowCpressure of the fuel supplied to the burnersDattemperator steam flow in the heater discharge circuit

单选题A compound gauge is typically installed on the ().Asuction side of a bilge pumpBexhaust manifold of an auxiliary dieselCdischarge line from an air compressorDchemical feed tank of an evaporator

单选题The exhaust valve opens before bottom dead center in a four stroke engine to() Ⅰ.allow for blow down Ⅱ.Reduce pumping lossesAⅠ onlyBⅡ onlyCboth Ⅰ and ⅡDneither Ⅰ nor Ⅱ

单选题Starting air valves are held firmly on their seats by()Acam rollers on the camshaftBspring forceCair pressure on top of the valve differential pistonDair pressure on the bottom of the valve differential piston

单选题If an auxiliary diesel engine frequently stalls, the trouble may be caused by ()Alow exhaust back pressureBair in the fuel systemCgasket blow-by or leakageDincorrect assembly of idler springs

单选题Which of the following conditions can cause above normal air temperature to develop in the intake manifold of a four-stroke/cycle turbo-charged diesel engine?()AClogged air intake faltersBPiston blow-byCA defective after-coolerDFaulty exhaust valves

单选题Temperature control valves installed in the jacket cooling water system of a diesel engine modulates the rate of water flow through the ().Acooling water pumpBnozzle cooling passagesCcylinder jacketsDheat exchanger

单选题Bottom blow valves are installed on auxiliary water-tube boilers to ()Acompletely drain the boiler in an emergencyBprevent sludge from forming in the drumCremove floating impurities from the boiler water surfaceDremove settled solids from the water drum

单选题If an operating auxiliary boiler has a water pH reading of 7, you should ().Abottom blow the boilerBtreat the water with caustic sodaCtreat the water with chemical scavengersDreduce the water alkalinity to recommended readings

单选题Which action should be taken when an auxiliary boiler in is operation?()AClean all electrical connectionsBLift the relief valves by handCInspect and clean all solenoid valvesDInspect for oil and water leaks