Sources for data on activity durations and resource requirements can be gathered from which of the following:A.Past project records (historical data)B.Commercial techniques (standard practices, rules of thumb)C.Past project team members knowledge (experience, oldtimers)D.All of the aboveE.A and C only

Sources for data on activity durations and resource requirements can be gathered from which of the following:

A.Past project records (historical data)

B.Commercial techniques (standard practices, rules of thumb)

C.Past project team members knowledge (experience, oldtimers)

D.All of the above

E.A and C only


相关考题:

Creation of project objectives:A.allows for data collection and analysis and progress reporting against which standards of performance can be measured.B.is accomplished by selection of measurable variables against which performance can be judged.C.is required before funding of the project by the project sponsor.D.all of the above.E.A and B only

Which of the following can the project manager use as a means of measuring project team effectiveness?A . AbsenteeismB . Sponsor-approved salary increasesC . Efficiency of the teamD . Turnover of personnelE . Grievances

Which of the following would most likely not be an essential objective of a project team kick-off meetingA . Create a project technology master planB . Get team members to know one anotherC . Identify project problem areasD . Obtain individual and group commitmentsE . Identify the project coordinator

Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A . MatrixB . Pure projectC . Project coordinatorD . Project expediterE . Classical/traditional

By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:A Significantly reduce project risksB eliminate project risksC provide a rational basis for better decision makingD identify risks, their impact(s), and any appropriate responsesE None of the above.

156 Expectancy theory as applied to project management implies that:A. The team will work the hardest on those goals that are clearly explained by the project managerB. The more rewards that the project manager provides, the better the performance of the teamC. Team members will work hardest for those project goals that also bring satisfaction to personal goalsD. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members E. None of the above

4 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A. MatrixB Pure projectC. Project coordinatorD. Project expediterE. Classical/traditional

118 Which of the following would most likely not be an essential objective of a project team kick-off meetingA. Create a project technology master planB. Get team members to know one anotherC. Identify project problem areasD. Obtain individual and group commitmentsE. Identify the project coordinator

86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A. MatrixB. Pure projectC. Project coordinatorD. Project expediterE. Classical/traditional

78 Which of the following can the project manager use as a means of measuring project team effectiveness?A. AbsenteeismB. Sponsor-approved salary increasesC. Efficiency of the teamD. Turnover of personnelE. Grievances

151 Sources for data on activity durations and resource requirements can be gathered from which of the following:A. Past project records (historical data)B. Commercial techniques (standard practices, rules of thumb)C. Past project team members knowledge (experience, oldtimers)D. All of the aboveE. A and C only

● Sources for data on activity durations and resource requirements can be gathered from which of the following:A Past project records (historical data)B Commercial techniques (standard practices, rules of thumb)C Past project team members knowledge (experience, oldtimers)D All of the aboveE A and C only

● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.(74)A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities

Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities

●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).(71)A.periodic project reports, periodic visits to the customer, and telephonic exchangesB.subordinates, project team members, and the project sponsorC.one-time reports, weekly reports, and monthly reportsD.the telephone, facsimile, and data transmission

Which of the following is the main feature of an OLTP application?() A.Summarized queriesB.Granular transactionsC.Voluminous historical dataD.Heterogeneous data sources

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.A.ParametricB.AnalogousC.Three-pointD.Expert judgment

The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project.The project manager maintains this link through( ).A.periodic project reports,periodic visits to the customer,and telephonic exchangesB.subordinates,project team members,and the project sponsorC.one-time reports,weekly reports,and monthly reportsD.the telephone,facsimile,and data transmission

()is a technique for estimating the duration or cost of activity or a projecy using historical data orm a similar activity or project.A.Analogous estimatingB.Parametric estimatingC.Three-Point estmatingD.Bottom-Up estimating

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project. A.Parametric B.Analogous C.Three-point D.Expert judgment

Which of the following is the main feature of an OLTP application?()A、Summarized queriesB、Granular transactionsC、Voluminous historical dataD、Heterogeneous data sources

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().A、crashing the scheduleB、performing resource levelingC、conducting reverse resource allocation schedulingD、utilizing the critical chain resources

The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)

Which factor has the greatest impact on the estimated per unit labor cost for a project?()A、Historical informationB、Use of outside vendorsC、Change control processesD、Human resource skill level requirements

A WebLogic team is developing an enterprise application from their desktop WebLogic environment. All development systems are connected to the same eight data sources for testing. As a WebLogic Administrator supporting this team, which two actions should you perform to free the developers from creating and configuring all the data sources on their desktop WebLogic environment?()A、Provide the team with a WebLogic domain template with the testing data sources configured.B、Provide the development team with a preconfigured domain archive file.C、Provide the development team with the [datasource] -jdbc.xml file to overwrite their local copy.D、Create the data sources on behalf each of the developer.E、Provide the development team with WLST scripts to create and configure the testing data  sources.

You are designing a Windows Azure application that will use Windows Azure Table storage. The application will allow teams of users to collaborate on projects.  Each user is a member of only one team. You have the following requirements:   - Ensure that each user can efficiently query records related to his or her team’s projects.  - Minimize data access latency.   You need to recommend an approach for partitioning table storage entities. What should you recommend? ()A、 Partition by user.B、 Partition by team.C、 Partition by project.D、 Partition by the current date.

单选题You are designing a Windows Azure application that will use Windows Azure Table storage. The application will allow teams of users to collaborate on projects.  Each user is a member of only one team. You have the following requirements:   - Ensure that each user can efficiently query records related to his or her team’s projects.  - Minimize data access latency.   You need to recommend an approach for partitioning table storage entities. What should you recommend? ()A Partition by user.B Partition by team.C Partition by project.D Partition by the current date.