In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on (74)A.the quality of the schedule and cost control analysisB.customer satisfactionC.customer compromise in defining its needsD.exceeding customer requirements through gold-plating

In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on (74)

A.the quality of the schedule and cost control analysis

B.customer satisfaction

C.customer compromise in defining its needs

D.exceeding customer requirements through gold-plating


相关考题:

Project trade-offs vary betweenA . risk, cost and schedule.B . direct cost, indirect cost, and resource availabilityC . quality, schedule and timeD . cost, quality and scheduleE . contract terms, scope and budget

The scope of a project can be expected to change if:A.The project manager must provide cost estimates without having a design conceptB.Oversimplification (underestimating) of the nature of the work occursC.The project manager is assigned after the project is defined, and the cost and schedule are approvedD.A clear objective is not providedE.All of the above are possible based upon the situation

Cost management includes processes that are required to maintain financial control of projects. These processes may include:A . economic evaluationB . cost estimatingC . cost forecastingD . B and CE . All of the above.

What is the relative priority of project Cost, Schedule and Quality?A . 1)Cost - 2)Schedule - 3)QualityB . 1)Quality - 2)Schedule - 3)CostC . 1)Quality - 2)Cost - 3)ScheduleD . 1)Schedule - 2)Quality - 3)CostE . All are of equal priority

A Project Status Report would include all of the following except:A Cost and schedule reportsB Changes to scope. cost or scheduleC Narrative explanation of variancesD Personnel problems on the projectE Upcoming activities

In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:A Work breakdown structureB milestone review and schedule techniqueC cost/schedule control systemD planning programming budget systemE program and evaluation review technique

130 What is the relative priority of project Cost, Schedule and Quality?A. 1)Cost - 2)Schedule - 3)QualityB. 1)Quality - 2)Schedule - 3)CostC. 1)Quality - 2)Cost - 3)ScheduleD. 1)Schedule - 2)Quality - 3)CostE. All are of equal priority

178 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:A. Work breakdown structureB. milestone review and schedule techniqueC. cost/schedule control systemD. planning programming budget systemE. program and evaluation review technique

127 Cost management includes processes that are required to maintain financial control of projects. These processes may include:A. economic evaluationB. cost estimatingC. cost forecastingD. B and CE. All of the above

41 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approvedD. A clear objective is not providedE. All of the above are possible based upon the situation

57 Which of the following are types of status reports?A. document, variance, trend and exceptionB. cost, trend, schedule and acquisitionC. cost, schedule, technical performanceD. analysis, cost, performance and scheduleE. All of the above.

72 Project trade-offs vary betweenA. risk, cost and schedule.B. direct cost, indirect cost, and resource availabilityC. quality, schedule and timeD. cost, quality and scheduleE. contract terms, scope and budget

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.A.estimatingB.definingC.planningD.sequencing

123 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not providedE. All of the above are possible based upon the situation

139 Which of the following are types of status reports?A. document, variance, trend and exceptionB. cost, trend, schedule and acquisitionC. cost, schedule, technical performanceD. analysis, cost, performance and scheduleE. All of the above

● Which of the following are types of status reports?A document, variance, trend and exceptionB cost, trend, schedule and acquisitionC cost, schedule, technical performanceD analysis, cost, performance and scheduleE All of the above.

● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.time estimatingB.cost estimatingC.project planningD.schedule development

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.A.accuracyB.approxinationC.specificationD.summary

On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.project planningB.time estimatingC.cost estimatingD.schedule development

Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT B.Resource levelling C.Schedule compression D.Critical chain method

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A、time estimatingB、cost estimatingC、project planningD、schedule development

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating

单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.Aactivity duration estimating, schedule developing, activity resource estimatingBactivity resource estimating, activity duration estimating, schedule developmentCschedule developing, activity resource estimating, activity duration estimatingDactivity resource estimating, schedule developing, activity duration estimating

单选题Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.空白(2)处填()AactivityBworkCcurrencyDtime