Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT B.Resource levelling C.Schedule compression D.Critical chain method

Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.

A.PERT B.Resource levelling C.Schedule compression D.Critical chain method


相关考题:

Which of the following tools and techniques can be used to collect information for the project closure reports?A Customer SurveysB BrainstormingC Document and Performance AnalysisD Lessons LearnedE All of the above

98 Which of the following tools and techniques can be used to collect information for the project closure reports?A. Customer SurveysB. BrainstormingC. Document and Performance AnalysisD. Lessons LearnedE. All of the above

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERTB.ResourcelevelingC.SchedulecompressionD.Critical chain method

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

● (73) is one of the techniques used for estimating activity durations.(73)A.Analogous EstimatingB.Precedence Diagramming Method (PDM)C.Dependency DeterminationD.Schedule network Templates

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.(72)A.PERTB.Resource levellingC.Schedule compressionD.Critical chain method

______is one of the techniques used for estimating activity durations.A.Analogous EstimatingB.Precedence Diagramming Method(PDM)C.Dependency DeterminationD.Schedule network Templates

According to Paul Leedy (1993: 17-42), which tools thatare useful for collecting a/the data are used by researchers?() A.The LibraryB.The ComputerC.MeasurementD.Statistics and Language

Difficult _____ the project was, I managed to finish it on schedule. A: no matterB: asC: despiteD: though

Which of the following tools can be used to schedule a backup operation that is to be run every Sunday evening?() A.JournalB.Task CenterC.Activity MonitorD.Command Line Processor

??Many useful tools and techniques are used in developing schedule.( 73) is a schedulenetwork analysis technique that modifies the project schedule to account for limited resource??A.PERTB. Resource levellingC.Schedule compressionD.Critical chain method

( )techniques are used to find ways to bring project activities that are alignment with the plan by fast tracking or crashing the schedule for the remaining work.A.Schedule forecastsB.Schedule compressionC.Change requestsD.Data analysis

A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations.(74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A. Duration analysis,activity-baseD.costing anD.informal bench markingB.Outcome analysis, technology analysis anD.activity eliminationC.Problem analysis, root cause analysis anD.critical path analysisD.Cost-benefit analysis, schedule analysis anD.risk analysis

Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating B.activity resource estimating, activity duration estimating, schedule development C.schedule developing, activity resource estimating, activity duration estimating D.activity resource estimating, schedule developing, activity duration estimating

Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERTB.Resource levellingC.Schedule compressionD.Critical chain methoD.

Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERT B.Resource levelling C.Schedule compression D.Critical chain methoD.

You are responsible for implementing maintenance jobs on a SQL Server 2005 database server. Certain jobs run every Sunday and other jobs run at the beginning of every month.  You need to schedule the jobs in the way that uses the least amount of administrative effort.  What should you do? ()A、 Create a job schedule that runs every Sunday. Assign weekly tasks to this schedule. Create a second schedule that runs on the first day of every month. Assign monthly tasks to this schedule. B、 Create a job for each task that runs once a day. Use a Transact-SQL statement to check the date and day of the week. If the day is either a Sunday or the first day of the month, execute the code. C、 Create a job schedule that runs once a day. Assign jobs to this job schedule. If the day is either a Sunday or the first day of the month, execute the jobs. D、 Create a job for each task that runs once a week on Sunday. Add a second job schedule that runs the job on the first of the month.

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.A、PERTB、ResourcelevelingC、SchedulecompressionD、Critical chain method

The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)

Which of the following tools can be used to identify the location of a network outage?()A、tracerouteB、netstatC、nslookupD、ping

Which of the following tools should be used to report current network status and is often used to check the reliability of a network?()A、 netpmonB、 netstatC、 nfsstatD、 vmstat

Which of the following tools can be used to schedule a backup operation that is to be run every Sunday evening?()A、JournalB、Task CenterC、Activity MonitorD、Command Line Processor

单选题Which of the following tools should be used to report current network status and is often used to check the reliability of a network?()A netpmonB netstatC nfsstatD vmstat

单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.Aactivity duration estimating, schedule developing, activity resource estimatingBactivity resource estimating, activity duration estimating, schedule developmentCschedule developing, activity resource estimating, activity duration estimatingDactivity resource estimating, schedule developing, activity duration estimating

单选题A system administrator is trying to troubleshoot company wide email problems that may be related to DNS.  Which of the following network tools would be MOST useful to determine if it is a DNS issue?()AnetstatBtracertCnslookupDping