130 What is the relative priority of project Cost, Schedule and Quality?A. 1)Cost - 2)Schedule - 3)QualityB. 1)Quality - 2)Schedule - 3)CostC. 1)Quality - 2)Cost - 3)ScheduleD. 1)Schedule - 2)Quality - 3)CostE. All are of equal priority
130 What is the relative priority of project Cost, Schedule and Quality?
A. 1)Cost - 2)Schedule - 3)Quality
B. 1)Quality - 2)Schedule - 3)Cost
C. 1)Quality - 2)Cost - 3)Schedule
D. 1)Schedule - 2)Quality - 3)Cost
E. All are of equal priority
相关考题:
Which of the following are types of status reports?Adocument, variance, trend and exceptionBcost, trend, schedule and acquisitionCcost, schedule, technical performanceDanalysis, cost, performance and scheduleEAll of the above.
Project tradeoffs are usually made by comparing _____ and constraints.ATime, cost, and qualityBTime, risk, and qualityCRisk, quality, and manpower availabilityDCost, quality, and technical performanceECost, quality, and risk
What is the relative priority of project Cost, Schedule and Quality?A . 1)Cost - 2)Schedule - 3)QualityB . 1)Quality - 2)Schedule - 3)CostC . 1)Quality - 2)Cost - 3)ScheduleD . 1)Schedule - 2)Quality - 3)CostE . All are of equal priority
12 What is the relative priority of project Cost, Schedule and Quality?A. 1)Cost - 2)Schedule - 3)QualityB. 1)Quality - 2)Schedule - 3)CostC. 1)Quality - 2)Cost - 3)ScheduleD. 1)Schedule - 2)Quality - 3)CostE. All are of equal priority
3 Project tradeoffs are usually made by comparing _____ and constraints.A. Time, cost, and qualityB. Time, risk, and qualityC. Risk, quality, and manpower availabilityD. Cost, quality, and technical performanceE. Cost, quality, and risk
57 Which of the following are types of status reports?A. document, variance, trend and exceptionB. cost, trend, schedule and acquisitionC. cost, schedule, technical performanceD. analysis, cost, performance and scheduleE. All of the above.
85 Project tradeoffs are usually made by comparing _____ and constraints.A. Time, cost, and qualityB. Time, risk, and qualityC. Risk, quality, and manpower availabilityD. Cost, quality, and technical performanceE. Cost, quality, and risk
139 Which of the following are types of status reports?A. document, variance, trend and exceptionB. cost, trend, schedule and acquisitionC. cost, schedule, technical performanceD. analysis, cost, performance and scheduleE. All of the above
● Project tradeoffs are usually made by comparing _____ and constraints.A Time, cost, and qualityB Time, risk, and qualityC Risk, quality, and manpower availabilityD Cost, quality, and technical performanceE Cost, quality, and risk