The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements
The Estimate Activity Resource process is closely coordinated with the (73)process.
(73)
A. Estimate Costs
B. Sequence Activities
C. Plan Communications
D. Conduct Procurements
相关考题:
A process characteristic has a true mean of 150 and a true standard deviation of 20. A sample of 25 items is taken from this process. The standard error of the estimate is:A . 0.2B . 0.8C . 4D . 5E . 7.5
● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(73)A. work performance informationB. scope statementC. change requestsD. process analysis
147 A process characteristic has a true mean of 150 and a true standard deviation of 20. A sample of 25 items is taken from this process. The standard error of the estimate is:A. 0.2B. 0.8C. 4D. 5E. 7.5
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.A.estimatingB.definingC.planningD.sequencing
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing
● (73) is one of the techniques used for estimating activity durations.(73)A.Analogous EstimatingB.Precedence Diagramming Method (PDM)C.Dependency DeterminationD.Schedule network Templates
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.(74)A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities
● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.time estimatingB.cost estimatingC.project planningD.schedule development
The Estimate Activity Resource process is closely coordinated with the(73) process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements
● The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements
Integration(73)is the process of verifying that the components of a system work together as described in the program design and system design specifications.(73)A.tryingB.checkingC.testing.D.coding
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities
The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing
PDM includes four types of dependencies or precedence relation ships:(73)The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
● Integration(73)is the process of verifying that the components of a system work together as described in the program design and system design specifications.(73)A. trying B. checking C. testing D. coding
●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).(73)A. project management planB. project baselineC. risk response planD. risk baseline
●In the following,which is not a method for inter-process communication? (73)(73) A. share memoryB.messageC.pipeD.memory copy
●Ravi, like many project (71) ,had studied the waterfall model of software development as the primary software life-cycle (72) .He was all set to use it for an upcoming project, his first assignment. However, Ravi found that the waterfall model could not be used because the customer wanted the software delivered in stages, something that implied that the system had to be delivered and built in (73) and not as (74) .The situation in many other projects is not very different. The real world rarely presents a problem in which a standard process, or the process used in a previous project, is the best choice.To be the most suitable, an existing process must be (75) to the new problem.Adevelopment process, even after tailoring, generally cannot handle change requests. To accommodate change requests without losing control of the project, you must supplement the development process with a requirement change management process.(71) A.customers B.managers C.users D.administrators(72) A.activity B.procedure C.process D.progress(73) A.parts B.modules C.software D.a whole(74) A.parts B.modules C.software D.a whole(75) A.modified B.used C.suited D.tailored
The operation of the Internet is closely monitored by the routers. When something unexpected occurs, the event will be reported by the protocol(73)。A.IGMPB.ICMPC.IPD.OSPF
PDM includes four types of dependencies or precedence relationships…(73),the initiation of the successor activity,depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
● Which of the following is not part of the quality assurance process?(73)(73)A.Operational definitionsB.Quality policyC.Quality auditsD.Quality improvement
A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations.(74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A.duration analysis anD.outcome analysisB.problem analysis anD.root cause analysisC.technology analysis anD.activity eliminationD.activity-baseD.costing anD.informal bench marking
A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations.(74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A. Duration analysis,activity-baseD.costing anD.informal bench markingB.Outcome analysis, technology analysis anD.activity eliminationC.Problem analysis, root cause analysis anD.critical path analysisD.Cost-benefit analysis, schedule analysis anD.risk analysis
The Estimate Activity Resource process is closely coordinated with the ( ) process. A.Estimate Costs B.Sequence Activities C.Plan Communications D.Conduct Procurements
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating
单选题On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.Atime estimatingBcost estimatingCproject planningDschedule development