The Estimate Activity Resource process is closely coordinated with the ( ) process. A.Estimate Costs B.Sequence Activities C.Plan Communications D.Conduct Procurements

The Estimate Activity Resource process is closely coordinated with the ( ) process.

A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements

参考解析

解析:

相关考题:

A process characteristic has a true mean of 150 and a true standard deviation of 20. A sample of 25 items is taken from this process. The standard error of the estimate is:A . 0.2B . 0.8C . 4D . 5E . 7.5

147 A process characteristic has a true mean of 150 and a true standard deviation of 20. A sample of 25 items is taken from this process. The standard error of the estimate is:A. 0.2B. 0.8C. 4D. 5E. 7.5

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.A.estimatingB.definingC.planningD.sequencing

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing

● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.(74)A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.time estimatingB.cost estimatingC.project planningD.schedule development

The Estimate Activity Resource process is closely coordinated with the(73) process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.A.milestoneB.baselineC.qualityD.work

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend

● The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements

● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.(74)A. milestoneB. baselineC. qualityD. work

●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities

The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing

On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.project planningB.time estimatingC.cost estimatingD.schedule development

A project is a [temporary] (请作答此空) of unique, complex, and connected activities having one goal or purpose and that must be completed by a specific time, within budget, and according to (Project management is the process of scoping, planning, staffing, organizing, directing, and controlling the development of a(n) ( ) system at a minimum cost within a specified time frame.For any systems development project, effective project management is necessary to ensure that the project meets the ( ), is eveloped within an acceptable budget, and fulfills customer expectations and specifications, Project management is a process that starts at the beginning of a project, extends through a project, and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process. Process management is an ongoing activity that documents, manages the use of, and improves an organization s chosen methodology (the"process")for system development, Process management is concemed with the activities, deliverables, and quallty standards to be applled to ( ) project(s).A.taskB.workC.sequenceD.activity

Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating B.activity resource estimating, activity duration estimating, schedule development C.schedule developing, activity resource estimating, activity duration estimating D.activity resource estimating, schedule developing, activity duration estimating

Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.A、milestoneB、baselineC、qualityD、work

Network Security is a continuous process. Which three phases apply to this process?()A、ConfigureB、ImproveC、OperateD、MonitorE、SecureF、Troubleshooting

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating

多选题Network Security is a continuous process. Which three phases apply to this process?()AConfigureBImproveCOperateDMonitorESecureFTroubleshooting

单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.AanalyzeBtrackClevelDextend

多选题Which three statements correctly describe the features of the I/O calibration process?()AOnly one I/O calibration process can run at a timeBIt automates the resource allocation for the Automated Maintenance TasksCIt improves the performance of the performance-critical sessions while runningDIt can be used to estimate the maximum number of I/Os and maximum latency time for the systemEThe latency time is computed only when the TIMED_STATISTICS initialization parameter is set to TRUE

单选题On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.Atime estimatingBcost estimatingCproject planningDschedule development

单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.Aactivity duration estimating, schedule developing, activity resource estimatingBactivity resource estimating, activity duration estimating, schedule developmentCschedule developing, activity resource estimating, activity duration estimatingDactivity resource estimating, schedule developing, activity duration estimating