78 The process of choosing/documenting the best approach to achieve the project objectives is part of: A. The scope baseline.B. Scope authorizationC. Scope definitionD. Scope planning.E. All of the above.

78 The process of choosing/documenting the best approach to achieve the project objectives is part of: A. The scope baseline.

B. Scope authorization

C. Scope definition

D. Scope planning.

E. All of the above.


相关考题:

Which of the following is not a scope management process?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

The project charter is prepared in which scope management process?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

Scope management is:A.a project control function.B.employs change control.C.a work authorization process.D.considers Cost, Quality and Schedule.E.All of the above.

The process of choosing/documenting the best approach to achieve the project objectives is part of:A.The scope baseline.B.Scope authorizationC.Scope definitionD.Scope planning.E.All of the above.

120 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments

140 In which of the following scope management processes are subject matter experts used? A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

141 The work breakdown structure (WBS) is first developed in which scope management process? A. InitiationB. Scope planningC. Scope change controlD. Scope DefinitionE. Scope verification

142 The project charter is prepared in which scope management process?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

143 In which of the following scope management processes is the scope management plan prepared?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

144 Which of the following is not a scope management process?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

146 Which of the following are included as part of a scope statement?A. Project justificationB. Project deliverablesC. Project objectivesD. All of the aboveE. B and C

160 The process of choosing/documenting the best approach to achieve the project objectives is part of:A. The scope baseline.B. Scope authorizationC. Scope definitionD. Scope planning.E. All of the above

● Which of the following are included as part of a scope statement?A Project justificationB Project deliverablesC Project objectivesD All of the aboveE B and C

● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

● Scope management is:A a project control function.B employs change control.C a work authorization process.D considers Cost, Quality and Schedule.E All of the above.

● The process of choosing/documenting the best approach to achieve the project objectives is part of:A The scope baseline.B Scope authorizationC Scope definitionD Scope planning.E All of the above.

is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A.WBS CreationB.Scope definitionC.Project acceptanceD.Scope verification

( ) describes, in detail, the project s deliverables and the work required to create those deliverables.A.Product scope description B.Project objectives C.Product specification D.The project scope statement

The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables. A、project scope statementB、work packageC、WBSD、project scope plan

● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)(74)A. Scope PlanningB. Scope VerificationC. Scope Change ControlD. Scope Definition

( ) describes,in detail,the project’s deliverables and the work required to create those deliverables. A.Product scope description B.Project objectives C.Stakeholder Analysis D.The project scope statement

() is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily. A.Project acceptance B.Scope verification C.Scope definition D.WBS Creation

The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.A.Project scope statementB.Work packageC.WBSD.Project scope plan

() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、projectacceptanceB、scopeverificationC、scopedefinitionD、WBS Creation

()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificationC、Scope definitionD、WBS Creation

单选题()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.AProject acceptanceBScope verificationCScope definitionDWBS Creation