The project charter is prepared in which scope management process?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification
The project charter is prepared in which scope management process?
A . Initiation
B . Scope planning
C . Scope Definition
D . Scope change control
E . Scope verification
相关考题:
● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.(71)A.riskB.problemC.resultD.data
Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.A.IntegrationB.ConfigurationC.ScopeD.Requirement
Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.A.riskB.problemC.resultD.data
Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.taskB.workC.sequenceD.activity
A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to(请作答此空).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.specificationB.rulesC.estimatesD.designs
()is a document?generated by the?creating?WBS?process?that?support the WBS,which provides?more?detailed?descriptions?of the components in the?WBS.A.The project?charterB.The?project?scope statementC.The?WBS dictionaryD.The?activity list
在实际的工作计划制定过程中,主要采用三种方法:“基于项目(Project-based)”,“基于流程(Process-based)”和基于时间(Time-based)。