对于()活动应该进行资源平衡(ResourceLeveling)。 A、时间安排很紧的(Tightscheduled)B、保持进度的(Onschedule)C、非关键路径上的(Non-CriticalPath)D、关键路径上的(CriticalPath)

对于()活动应该进行资源平衡(ResourceLeveling)。

A、时间安排很紧的(Tightscheduled)

B、保持进度的(Onschedule)

C、非关键路径上的(Non-CriticalPath)

D、关键路径上的(CriticalPath)


相关考题:

资源平衡(Resourceleveling)() A、通过安排项目进度、减少资源时间,来处理资源的有效使用B、一般情况下可能对活动历时没有影响C、可能延长原始项目完成日期D、A与C

Resource leveling _____.A.Allocates resources to activities to find shortest schedule within fixed resource limits.B.Smoothes out resource requirements by rescheduling activities within their float time.C.Smooths out resource requirements by substituting activities with unassigned resources.D.Attempts to reduce resource requirements within a constraint on project durationE.B or D

Planning activities such that predetermined resource availability pools are not exceeded is called:A.Resource leveling.B.Manpower leveling.C.Resource limited planning.D.Manpower planning.E.Manpower contingency planning.

171 Resource leveling _____.A. Allocates resources to activities to find shortest schedule within fixed resource limits.B. Smoothes out resource requirements by rescheduling activities within their float time.C. Smooths out resource requirements by substituting activities with unassigned resources.D. Attempts to reduce resource requirements within a constraint on project durationE. B or D

53 Resource leveling _____.A. Allocates resources to activities to find shortest schedule within fixed resource limits.B. Smoothes out resource requirements by rescheduling activities within their float time.C. Smooths out resource requirements by substituting activities with unassigned resources.D. Attempts to reduce resource requirements within a constraint on project durationE. B or D

● Resource leveling _____.A Allocates resources to activities to find shortest schedule within fixed resource limits.B Smoothes out resource requirements by rescheduling activities within their float time.C Smooths out resource requirements by substituting activities with unassigned resources.D Attempts to reduce resource requirements within a constraint on project durationE B or D

对多项目进行进度计划编制和资源时,以下哪项参数将受到影响?A、 资源命名用和资源平衡B、 历时压缩和模拟C、 活动清单和工作分解结构D、 进度计划滑动和进行中存货

在制订进度计划时,已经完成了:①绘制进度网络图;②活动资源估算;③活动历时估算。此时,为了确定各项活动的时差可进行( ).A:资源平衡分析B:进度压缩分析C:关键路线分析D:假设情景分析

在项目组合管理中,在主旨范围内为项目分配资源。组织级项目管理中的资源平衡过程主要是: ( ) 。的说法是正确的。A. 首先为单个项目做资源平衡,再在项目间进行资源平衡B. 针对所有项目的需求对组织内的资源进行统一的资源平衡C. 只在单一项目内进行资源平衡D. 主要针对资源短缺的项目进行资源优化与平衡