资源平衡(Resourceleveling)() A、通过安排项目进度、减少资源时间,来处理资源的有效使用B、一般情况下可能对活动历时没有影响C、可能延长原始项目完成日期D、A与C

资源平衡(Resourceleveling)()

A、通过安排项目进度、减少资源时间,来处理资源的有效使用

B、一般情况下可能对活动历时没有影响

C、可能延长原始项目完成日期

D、A与C


相关考题:

对于()活动应该进行资源平衡(ResourceLeveling)。 A、时间安排很紧的(Tightscheduled)B、保持进度的(Onschedule)C、非关键路径上的(Non-CriticalPath)D、关键路径上的(CriticalPath)

Resource leveling _____.A.Allocates resources to activities to find shortest schedule within fixed resource limits.B.Smoothes out resource requirements by rescheduling activities within their float time.C.Smooths out resource requirements by substituting activities with unassigned resources.D.Attempts to reduce resource requirements within a constraint on project durationE.B or D

Planning activities such that predetermined resource availability pools are not exceeded is called:A.Resource leveling.B.Manpower leveling.C.Resource limited planning.D.Manpower planning.E.Manpower contingency planning.

34 Planning activities such that predetermined resource availability pools are not exceeded is called: A. Resource leveling.B. Manpower leveling.C. Resource limited planning.D. Manpower planning.E. Manpower contingency planning

171 Resource leveling _____.A. Allocates resources to activities to find shortest schedule within fixed resource limits.B. Smoothes out resource requirements by rescheduling activities within their float time.C. Smooths out resource requirements by substituting activities with unassigned resources.D. Attempts to reduce resource requirements within a constraint on project durationE. B or D

116 Planning activities such that predetermined resource availability pools are not exceeded is called: A. Resource leveling.B. Manpower leveling.C. Resource limited planning.D. Manpower planning.E. Manpower contingency planning.

53 Resource leveling _____.A. Allocates resources to activities to find shortest schedule within fixed resource limits.B. Smoothes out resource requirements by rescheduling activities within their float time.C. Smooths out resource requirements by substituting activities with unassigned resources.D. Attempts to reduce resource requirements within a constraint on project durationE. B or D

● Resource leveling _____.A Allocates resources to activities to find shortest schedule within fixed resource limits.B Smoothes out resource requirements by rescheduling activities within their float time.C Smooths out resource requirements by substituting activities with unassigned resources.D Attempts to reduce resource requirements within a constraint on project durationE B or D

【单选题】下面哪个说法正确?A.库存可以平衡客户资源也可以平衡生产资源B.库存可以平衡客户资源但不能平衡生产资源C.库存不能平衡客户资源但可以平衡生产资源D.库存即不能平衡客户资源也不能平衡生产资源