Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:A.All activities.B.Only those activities with the longest time durations.C.Those activities on the critical path begining with the longest time duration activities.D.Those activities with the greatest degree of risk.E.None of the above.

Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:

A.All activities.

B.Only those activities with the longest time durations.

C.Those activities on the critical path begining with the longest time duration activities.

D.Those activities with the greatest degree of risk.

E.None of the above.


相关考题:

Free float is the amount of time that an activity may be delayed with out affecting the _____.A.Early start of the succeeding activities.B.Late start of the succeeding activities.C.Project finish.D.Cost of the project.E.None of the above.

Increasing resources on the critical path activities may not always shorten the length of the project because:A.Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).B.Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.C.The skill level of the added resources might not be appropriate for the activities to be performed.D.Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)E.All of the above.

During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A . The project will be completed late.B . The critical path has been lengthened.C . the costs are being overrun.D . Overtime will be required to maintain the original critical path.E . None of the above.

Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A . PB . QC . RD . SE . T

The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work?A . MatrixB . ClassicalC . ExpediterD . CoordinatorE . Pure project

111 Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:A. All activities.B. Only those activities with the longest time durations.C. Those activities on the critical path begining with the longest time duration activities.D. Those activities with the greatest degree of risk.E. None of the above

163 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A. The project will be completed late.B. The critical path has been lengthened.C. the costs are being overrun.D. Overtime will be required to maintain the original critical path.E. None of the above.

112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A. PB. QC. RD. SE. T

● Free float is the amount of time that an activity may be delayed with out affecting the _____.A Early start of the succeeding activities.B Late start of the succeeding activities.C Project finish.D Cost of the project.E None of the above.

● Increasing resources on the critical path activities may not always shorten the length of the project because:A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.C The skill level of the added resources might not be appropriate for the activities to be performed.D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)E All of the above.

● Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:A All activities.B Only those activities with the longest time durations.C Those activities on the critical path begining with the longest time duration activities.D Those activities with the greatest degree of risk.E None of the above.

The(70)provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.contractC.project human resource planD.project charter

The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders

The( )provides the project manager with the authority to apply organizational resources to project activities。A.project management planB.project charterC.project human resource planD.project stakeholders

In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.A.scheduleB.WBSC.SOWD.charter

The (73) provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.project charterC.project human resource planD.project stakeholders

In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.A.scheduleB.activityC.planD.contractor@@@SXB@@@A.findingB.balanceC.allocationD.distribution

The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.A.Contingency reserveB.Project profitC.Management reserveD.Special fund

In order to facilitate configuration and change management, manual or automated tools maybe used. Tools selection should be based on the needs of the( ).A. Project managerB.CCB.membersC.Project stakeholdersD. Project Management Office(PMO)

In project time management processes, ( )involves identifying and documenting the relationships between project activities.A.activity definitionB.activity sequencingC.schedule controlD.schedule development

Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project

A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.taskB.workC.sequenceD.activity

In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.A、scheduleB、activityC、planD、contractor

The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、project charter

The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、projectcharter

单选题The()provides the project manager with the authority to apply organizational resources to project activities.Aproject management planBcontractCproject human resource planDprojectcharter

单选题The()provides the project manager with the authority to apply organizational resources to project activities.Aproject management planBcontractCproject human resource planDproject charter