111 Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:A. All activities.B. Only those activities with the longest time durations.C. Those activities on the critical path begining with the longest time duration activities.D. Those activities with the greatest degree of risk.E. None of the above
111 Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:
A. All activities.
B. Only those activities with the longest time durations.
C. Those activities on the critical path begining with the longest time duration activities.
D. Those activities with the greatest degree of risk.
E. None of the above
相关考题:
Which influence reflects an informal organization?A . formal authorityB . reward powerC . referent powerD . expert powerE . penalty
The type of power most infrequently used by the PM isA . formal authorityB . reward powerC . referent powerD . expert powerE . penalty
Rodman met with Tony to try and settle the dispute over their contract.A:markB:involveC:solveD:avoid
He has made up his mind to give up smoking.A:tried B:attemptedC:agreed D:decided