单选题If the ship is delayed by reason of Charterer’s failure to name a port,()will be liable for the damages.Athe ownerBthe ChartererCthe shipperDthe carrier
单选题
If the ship is delayed by reason of Charterer’s failure to name a port,()will be liable for the damages.
A
the owner
B
the Charterer
C
the shipper
D
the carrier
参考解析
解析:
暂无解析
相关考题:
If the Charterer nominates an unsafe port and the ship is damaged through going there, ________ will be liable for the damage, subject to that the master acts reasonably in going there.A.heB.herC.the ownerD.the shipper
Where the Shipowner has accepted the port of discharge named by the Charterer,he must go there although it is not prospectively safe,and claim damages for injury ______ the ship by reason of the port not being safe.A.byB.onC.toD.in
A claim for cargo damages may be held against the shipowner if such damage is the result of failure of the ship's officers to ______.A.ensure the fitness and safety of cargo spacesB.ensure adequate packaging of the cargoC.prevent delays due to quarantine restrictionsD.correct all defects in the ship's construction
A charterer is unable to complete the loading of a vessel during the lay days specified in the charter party. Under these circumstances,the ______.A.vessel operator can collect demurrageB.ship is authorized extra time to discharge the cargoC.charterer must pay dispatch moneyD.effective period of the charter is extended
If a chartered ship is prevented from,or delayed in,getting to the loading port by peril excepted during the voyage,the exception clauses ______.A.applyB.complyC.supplyD.reply
Usually the Charterer has to redeliver the ship in the same good order ______ when delivered,fair wear and tear excepted.A.inB.byC.onD.as
If the redelivery of a vessel is delayed by causes ______,hire is payable at the charter rate until redelivery even though the market rate may have gone up or down.A.for which neither party is responsibleB.for which the owner is responsibleC.for which either party is responsibleD.for which the charterer is responsible
Apart from special contract or statute every Shipowner is ______ a liability akin to that of a common carrier,irrespective of whether the goods were shipped by a Charterer or on a general ship.A.onB.inC.underD.at
It should be noted that laydays do not begin to run ______ the ship is,so far as she is concerned,ready to receive or discharge cargo,unless she would have been ready except for the Charterer's default.A.whenB.at the time thatC.untilD.as soon as
请选择合适的选项,替换句中括号处:I am sorry for the delayed response (dueto) the weekend.()A、because ofB、by reason ofC、on account ofD、because
When the charterer uses more time than time stipulated in a voyage C/P to load his cargo, the ship-owner is entitled to()A、overtimeB、dispatchC、demurrageD、deadfreight
单选题The meaning of slacken her speed is().Aincrease ship's speedBslow down ship's speedCmake up ship's speedDfix up shp's speed
单选题Where the Shipowner has accepted the port of discharge named by the Charterer,he must go there although it is not prospectively safe,and claim damages for injury()the ship by reason of the port not being safe.AbyBonCtoDin
单选题The reason for the obligation to load a full cargo()that otherwise the Shipowner would lose freight on account of some part of the ship’s carrying capacity not being utilized.AisBmakesChasDtakes
单选题If the redelivery of a vessel is delayed by causes (),hire is payable at the charter rate until redelivery even though the market rate may have gone up or down.Afor which neither party is responsibleBfor which the owner is responsibleCfor which either party is responsibleDfor which the charterer is responsible
单选题Which statement concerning reserve sources of energy for GMDSS is FALSE().AWhile the ship is at sea,there must be available at all times a supply of electrical energy sufficient to operate the radio installations and to charge any batteries used as part of a reserve source of energyBBoth the VHF and MF/HF installations must be simultaneously suppliedCA means of ensuring a continuous supply of electrical power must be provided to all GMDSS equipment that could be affected by an interruption in powerDIf a UPS or equivalent is used to supply power to the ship's GPS receiver or other source of positional information,a means must be provided to ensure the continuous supply of the information in the event of a failure to the ship's main or emergency source of power
单选题The apparent wind can be zero when the true wind is from().Aahead and equal to the ship's speedBastern and equal to the ship's speedCahead and equal to twice the ship's speedDastern and equal to twice the ship's speed
单选题Usually the Charterer has to redeliver the ship in the same good order()when delivered,fair wear and tear excepted.AinBbyConDas
单选题The consignee’s refusal to take delivery,or failure to do so within a reasonable time,also puts an end to()liability as a carrier.Athe Shipowner'sBthe Charterer'sCthe cargo owner's
单选题Apart from special contract or statute every Shipowner is()a liability akin to that of a common carrier,irrespective of whether the goods were shipped by a Charterer or on a general ship.AonBinCunderDat
单选题If a chartered ship is prevented from,or delayed in,getting to the loading port by peril excepted during the voyage,the exception clauses().AapplyBcomplyCsupplyDreply
单选题If the Shipowner fails to give the Charterer the notice of readiness to load,and delay in commencing to load is thereby caused,the Charterer will(),as he is not bound to look out for the ship.Abe responsibleBnot be responsibleCpay the Shipowner for the expenses incurredDnot claim the Shipowner for the expenses incurred
单选题A claim for cargo damages may be held against the shipowner if such damage is the result of failure of the ship’s officers to().Aensure the fitness and safety of cargo spacesBensure adequate packaging of the cargoCprevent delays due to quarantine restrictionsDcorrect all defects in the ship's construction
单选题Contracts whereby the possession and control of a ship vest()the Charterer are becoming more common today especially in the oil tanker trade.AonBtoCatDin
单选题A claim for cargo damages may be held against the ship owner if such damage is the result of failure of the ship’s officers to().Acorrect all defects in the ship's constructionBensure the fitness and safety of cargo spacesCensure adequate packaging of the cargoDprevent delays due to quarantine restrictions
单选题The loading of the ship must be done in accordance with().Athe ship’s instructionsBthe terminal’s instructionsCthe port captain’s instructionsDthe charterer’s instructions