If the redelivery of a vessel is delayed by causes ______,hire is payable at the charter rate until redelivery even though the market rate may have gone up or down.A.for which neither party is responsibleB.for which the owner is responsibleC.for which either party is responsibleD.for which the charterer is responsible

If the redelivery of a vessel is delayed by causes ______,hire is payable at the charter rate until redelivery even though the market rate may have gone up or down.

A.for which neither party is responsible

B.for which the owner is responsible

C.for which either party is responsible

D.for which the charterer is responsible


相关考题:

A charterer is unable to complete the loading of a vessel during the lay days specified in the charter party. Under these circumstances,the ______.A.vessel operator can collect demurrageB.ship is authorized extra time to discharge the cargoC.charterer must pay dispatch moneyD.effective period of the charter is extended

In a charter-party,the amount of despatch money payable is often fixed ______.A.at one fourth the demurrage rateB.at one third the demurrage rateC.at half the demurrage rateD.at the demurrage rate

Off hire is when a vessel breaks down,strands,or has any damage that prevents the working of cargo or delays the sailing of the vessel.Under which of the following charter parties is off hire most likely to be mentioned? ______.A.BareboatB.VoyageC.TimeD.Lease

According to SINOTIME Charter In the event of loss of time due to __________,hire will not cease.A.detention of or interference with the Vessel by any authorities in consequence of legal action against,or breach of regulations by the Owners,Master,Officers or CrewB.stoppages resulting from any breach of this Charter by the OwnersC.deviation,putting back or putting into any port other than that to which she is bound under the instructions of Charterers for any reason or for any purposeD.reasonable deviation

The S.S. Hollowpoint has a charter party in which the charterer assumes no responsibility for the operation of the vessel but pays stevedoring expenses. What is the name of the charter party? ______.A.BareboatB.DispatchC.VoyageD.Demise

A vessel has a charter party for one voyage to carry a full load of manganese from Durban,South Africa,to Baltimore,Maryland,at a stipulated rate per ton. Which type of contract is involved? ______.A.Bareboat charter partyB.Voyage charter partyC.Demise charter partyD.Time charter party

The owners of the S.S. Short Haul agree to a charter with the Longsplice Steamship Company. The owners stipulate in the charter party that the regular Master must be employed as the vessel's Master for the entire life of the contract. Which charter has beA.BareboatB.LeaseC.TimeD.Voyage

__________ the parties agree to cancel the Charter,the Owners to indemnify the Brokers against any loss of brokerage,but in such case the brokerage not to exceed that on one year's hire.A.WouldB.ShouldC.HadD.Might

If the full hire is not paid owing to breach of charter by either of the parties the party liable __________ to indemnify the Brokers against their loss of brokerage.A.therewithB.thereforC.thereofD.thereby

In Bareboat Charter,the Owners and Charterers shall ______ appoint surveyors for the purpose of determining and agreeing in writing the condition of the Vessel at the time of delivery and redelivery hereunder.A.eachB.jointlyC.severallyD.both together

翻译:All bunkers used by the Vessel while off hire shall be the Owner’s account。

翻译:Prior to delivery and redelivery of the vessel the parties shall each appoint surveyors。

In marine voyage chartering, the following()terms are normally appeared in the voyage charter party.A、freight paymentB、hire paymentC、lay-timeD、demurrage

单选题According to SINOTIME Charter In the event of loss of time due to(),hire will not cease.Adetention of or interference with the Vessel by any authorities in consequence of legal action against,or breach of regulations by the Owners,Master,Officers or CrewBstoppages resulting from any breach of this Charter by the OwnersCdeviation,putting back or putting into any port other than that to which she is bound under the instructions of Charterers for any reason or for any purposeDreasonable deviation

问答题翻译:All bunkers used by the Vessel while off hire shall be the Owner’s account。

单选题According to Sinotime,during the period of this Charter,should the Vessel be requisitioned by the government of the Vessel’s nationality,hire to()from the time of her requisition.AcontinueBstopCcommenceDcease

单选题Off hire is when a vessel breaks down,strands,or has any damage that prevents the working of cargo or delays the sailing of the vessel.Under which of the following charter parties is off hire mostlikely to be mentioned?().ABareboatBVoyageCTimeDLease

单选题A right to withdraw a vessel()the service of the Charterers failing the punctual and regular payment of the hire cannot be defeated by later tender of the hire.AinBbeforeCfromDagainst

单选题If the redelivery of a vessel is delayed by causes (),hire is payable at the charter rate until redelivery even though the market rate may have gone up or down.Afor which neither party is responsibleBfor which the owner is responsibleCfor which either party is responsibleDfor which the charterer is responsible

问答题翻译:Prior to delivery and redelivery of the vessel the parties shall each appoint surveyors。

单选题A vessel has a charter party for one voyage to carry a full load of manganese from Durban,South Africa,to Baltimore,Maryland,at a stipulated rate per ton. Which type of contract is involved? ()ABareboat charter partyBVoyage charter partyCDemise charter partyDTime charter party

单选题()payment of the hire the Owners may withdraw the Vessel from the service of Charterers,without prejudice to any claim Owners may otherwise have on Charterers under this Charter.AIn the event ofBIn default ofCIn spite ofDIn respect of

单选题The S.S. Hollowpoint has a charter party in which the charterer assumes no responsibility for the operation of the vessel but pays stevedoring expenses. What is the name of the charter party? ().ABareboatBDispatchCVoyageDDemise

单选题The owners of the S.S. Short Haul agree to a charter with the Longsplice Steamship Company. The owners stipulate in the charter party that the regular Master must be employed as the vessel’s Master for the entire life of the contract. Which charter has be ().ABareboatBLeaseCTimeDVoyage

单选题The Owners to take over and pay all fuel remaining in the Vessel’s bunkers on re-delivery at current price at the port of redelivery,or at the nearest main bunkering port,if the bunker price at the port of redelivery is not available. This indicates that the Owners are to take over and pay the remaining bunkers().Aat current price at the nearest main bunkering portBat current price at the port of redelivery if it is not available to obtain the current price at the nearest main bunkering portCat current price at the nearest main bunkering port if it is cheaper than that at the port of redeliveryDat current price at the port of redelivery if it is obtainable,even the price is higher at the nearest main bunkering port

单选题()is a charter form,in which the bare ship is chartered without crew and Charterer takes over the vessel with a minimum of restrictions.ATime CharterBTrip CharterCDemise CharterDVoyage Charter

单选题Off hire is when a vessel breaks down,strands,or has any damage that prevents the working of cargo or delays the sailing of the vessel.Under which of the following charter parties is off hire most likely to be mentioned?().ABareboatBVoyageCTimeDLease