( )is one of the tools and techniques of Sequence Activities. A.Decomposition B.Fish bone Diagram C.Precedence Diagramming MethoD. D.Expert Judgment

( )is one of the tools and techniques of Sequence Activities.

A.Decomposition
B.Fish bone Diagram
C.Precedence Diagramming MethoD.
D.Expert Judgment

参考解析

解析:翻译:前导图法是活动排序的工具和技术之一。 A.分解 B.鱼骨图C.PDM图 D.专家判断

相关考题:

Which of the following tools and techniques can be used to collect information for the project closure reports?A Customer SurveysB BrainstormingC Document and Performance AnalysisD Lessons LearnedE All of the above

98 Which of the following tools and techniques can be used to collect information for the project closure reports?A. Customer SurveysB. BrainstormingC. Document and Performance AnalysisD. Lessons LearnedE. All of the above

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERTB.ResourcelevelingC.SchedulecompressionD.Critical chain method

Development is a structured design methodology that proceeds in a sequence from one phase to the next.A.WaterfallB.PhasedC.PrototypingD.Parallel

● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.(72)A.PERTB.Resource levellingC.Schedule compressionD.Critical chain method

______is one of the techniques used for estimating activity durations.A.Analogous EstimatingB.Precedence Diagramming Method(PDM)C.Dependency DeterminationD.Schedule network Templates

●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.(71)A. BenchmarkingB. Quality metricC. Quality checklistD. Brainstorming

one excellent way to make speaking tasks communicative is to use information-gap activities.() 此题为判断题(对,错)。

All the following tools and techniques are helpful to accurately confirming customers’needs,except( 72 )。A.questionnairesB.prototyping approachesC.fishbone diagramsD.interviews

all of the following tools and techniques are helpful to acurately confirming customers needsexcept ()A.questionnairesB.prototyping approachesC.fishbone diagramsD.interviews

Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT B.Resource levelling C.Schedule compression D.Critical chain method

??Many useful tools and techniques are used in developing schedule.( 73) is a schedulenetwork analysis technique that modifies the project schedule to account for limited resource??A.PERTB. Resource levellingC.Schedule compressionD.Critical chain method

() is one of the tools and techniques.A.DecompositionB.Fishbone DiagramC.Precedence Diagramming Method of Sequence ActivitiesD.Expert Judgment

● (75) Development is a structured design methodology that proceeds in a sequence from one phase to the next.(75)A. WaterfallB. PhasedC. PrototypingD. Parallel

Approaching a anchorage in fog, you hear one short, one prolonged, and one short blast in that sequence on a ship’s whistle. This indicates ______.A.A vessel towedB.A vessel not under command and unable to maneuver.C.A vessel anchored giving warning of her position.D.A vessel stopped dead in the water.

( )is one of the tools and techniques. A.Decomposition B.Fish bone Diagram C.Precedence Diagramming MethoD.of Sequence Activities D.Expert Judgment

Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERTB.Resource levellingC.Schedule compressionD.Critical chain methoD.

all the following tools and techniques are helpful to accurately confirming customers needs,except ( ) A.questionnaires B.prototyping approaches C.fishbone diagrams D.interviews

Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERT B.Resource levelling C.Schedule compression D.Critical chain methoD.

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.A、PERTB、ResourcelevelingC、SchedulecompressionD、Critical chain method

Cindy wants to set up third-party tools so she can access them via the designer. Which one of  the following should cindy do?()A、 file- inport B、 tools-import C、 tools-add tools D、 shared resources-third party tools

单选题all of the following tools and techniques are helpful to acurately confirming customers needs except ()AquestionnairesBprototyping approachesCfishbone diagramsDinterviews

单选题Cindy wants to set up third-party tools so she can access them via the designer. Which one of  the following should cindy do?()A file- inport B tools-import C tools-add tools D shared resources-third party tools

多选题Which two statements about sequences are true? ()AYou use a NEXTVAL pseudo column to look at the next possible value that would be generated from a sequence, without actually retrieving the value.BYou use a CURRVAL pseudo column to look at the current value just generated from a sequence, without affecting the further values to be generated from the sequence.CYou use a NEXTVAL pseudo column to obtain the next possible value from a sequence by actually retrieving the value from the sequence.DYou use a CURRVAL pseudo column to generate a value from a sequence that would be used for a specified database column.EIf a sequence starting from a value 100 and incremented by 1 is used by more than one application, then all of these applications could have a value of 105 assigned to their column whose value is being generated by the sequence.FYou use a REUSE clause when creating a sequence to restart the sequence once it generates the maximum value defined for the sequence.

单选题Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.ABenchmarkingBQuality metricCQuality checklistDBrainstorming

单选题Approaching an anchorage in fog,you hear one short,one prolonged,and one short blast in that sequence on a ship’s whistle. This indicates().AA vessel towedBA vessel not under command and unable to maneuverCA vessel anchored giving warning of her positionDA vessel stopped dead in the water

单选题The term () refers to one complete sequence of operations required to produce power in an engine.Adiesel engineBstrokeCcycleDcompression ratio