??Many useful tools and techniques are used in developing schedule.( 73) is a schedulenetwork analysis technique that modifies the project schedule to account for limited resource??A.PERTB. Resource levellingC.Schedule compressionD.Critical chain method

??Many useful tools and techniques are used in developing schedule.( 73) is a schedule

network analysis technique that modifies the project schedule to account for limited resource

??

A.PERT

B. Resource levelling

C.Schedule compression

D.Critical chain method


相关考题:

Which of the following tools and techniques can be used to collect information for the project closure reports?A Customer SurveysB BrainstormingC Document and Performance AnalysisD Lessons LearnedE All of the above

98 Which of the following tools and techniques can be used to collect information for the project closure reports?A. Customer SurveysB. BrainstormingC. Document and Performance AnalysisD. Lessons LearnedE. All of the above

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERTB.ResourcelevelingC.SchedulecompressionD.Critical chain method

● (73) is one of the techniques used for estimating activity durations.(73)A.Analogous EstimatingB.Precedence Diagramming Method (PDM)C.Dependency DeterminationD.Schedule network Templates

What you need is just a computer, because you can_____easily get on Internet. A.many useful informationsB.much useful informationC.some useful informationsD.a lot of useful informations

Stack is quite simple. Many computer systems have stacks built into their circuitry. They also have machine-level instructions to operate the hardware stack. Stack is(73)in computer systems.A.uselessB.not importantC.simple but importantD.too simple to be useful

● C++ is used with proper (73) design techniques.(73)A. object-orientedB. object-basedC. face to objectD. face to target

● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.(72)A.PERTB.Resource levellingC.Schedule compressionD.Critical chain method

According to Paul Leedy (1993: 17-42), which tools thatare useful for collecting a/the data are used by researchers?() A.The LibraryB.The ComputerC.MeasurementD.Statistics and Language

C++ is used with proper(73)design techniques.A.object-orientedB.object-basedC.face to objectD.face to target

All the following tools and techniques are helpful to accurately confirming customers’needs,except( 72 )。A.questionnairesB.prototyping approachesC.fishbone diagramsD.interviews

all of the following tools and techniques are helpful to acurately confirming customers needsexcept ()A.questionnairesB.prototyping approachesC.fishbone diagramsD.interviews

Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT B.Resource levelling C.Schedule compression D.Critical chain method

Accelerated analysis approaches emphasize the construction of (71) to more rapidly identify business and user requirements for a new system. As an accelerated analysis technology,(72) reads the program code and automatically generates the equivalent system model, and the code can be obtained from (73) All system analysis approaches require some form. of (74) which includes those techniques to be used to identify or extract system problems and solution requirements from user community.(75) is a classical set of techniques used to collect information about system problems, opportunities, solution requirements, and priorities.A.object modelsB.prototypesC.use casesD.components

We can infer from the passage that_____.[A] Shearer has experienced many violent incidents [B] new tools have been used to investigate terrorists[C] FBI has been active in the war on eco-terrorism [D] ELF openly declares its beliefs and ends

● Stack is quite simple. Many computer systems have stacks built into their circuitry. They also have machine-level instructions to operate the hardware stack. Stack is (73)in computer systems.(73)A.uselessB.not importantC.simple but importantD.too simple to be useful

Onboard a Ro-Ro vessel many decks are used for the carriage of both rolling and container cargoes,as such it is most useful if a deck socket accepts both ______.A.Twist-Locks and lashing hooksB.Container locks and bridge fittingsC.Bridge fittings and lashing hooksD.Twist-locks and container locks

A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations.(74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A.automationB.modelingC.improvementD.re-engineering

A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations.(74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A.duration analysis anD.outcome analysisB.problem analysis anD.root cause analysisC.technology analysis anD.activity eliminationD.activity-baseD.costing anD.informal bench marking

A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations.(74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A. Duration analysis,activity-baseD.costing anD.informal bench markingB.Outcome analysis, technology analysis anD.activity eliminationC.Problem analysis, root cause analysis anD.critical path analysisD.Cost-benefit analysis, schedule analysis anD.risk analysis

Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERTB.Resource levellingC.Schedule compressionD.Critical chain methoD.

Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERT B.Resource levelling C.Schedule compression D.Critical chain methoD.

What are the main techniques used in a Grammar-Translation classroom?

钮锁、拉杆、桥锁、桥板是用于绑扎集装箱的工具。()A、Lashing bars, twist locks, bridge plates and bridge fittings are tools used for lashing containers.B、Twist locks, bridge plates, bridge fittings and lashing bars are tools used for lashing containers.C、Twist locks, lashing bars, bridge fittings and bridge plates are tools used for lashing containers.D、Lashing bars, bridge fittings, bridge plates and twist locks are tools used for lashing containers.

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.A、PERTB、ResourcelevelingC、SchedulecompressionD、Critical chain method

The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)

单选题all of the following tools and techniques are helpful to acurately confirming customers needs except ()AquestionnairesBprototyping approachesCfishbone diagramsDinterviews