()is a document?generated by the?creating?WBS?process?that?support the WBS,which provides?more?detailed?descriptions?of the components in the?WBS.A.The project?charterB.The?project?scope statementC.The?WBS dictionaryD.The?activity list

()is a document?generated by the?creating?WBS?process?that?support the WBS,which provides?more?detailed?descriptions?of the components in the?WBS.

A.The project?charter
B.The?project?scope statement
C.The?WBS dictionary
D.The?activity list

参考解析

解析:本题翻译:()是由支持WBS的创建WBS过程生成的文档,它提供了WBS中组件的更详细描述。
A.项目章程B.项目范围说明书C.WBS词典D.活动列表
本题考查的是范围管理中的WBS词典,正确选项为C:WBS词典。
在制作WBS的过程中,要给WBS的每个部分赋予一个账户编码标志符,它们是成本、进度和资源使用信息汇总的层次结构。需要生成一些配套的文件,这些文件需要和WBS配套使用,称为WBS词典。所以说WBS词典是创建WBS过程生成的支持WBS的文档,它提供了WBS中组件的更详细描述。

相关考题:

The work breakdown structure (WBS) is first developed in which scope management process?A . InitiationB . Scope planningC . Scope change controlD . Scope DefinitionE . Scope verification

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level() A.independentresourceB.individualworkloadC.workmilestoneD.workpackage

141 The work breakdown structure (WBS) is first developed in which scope management process? A. InitiationB. Scope planningC. Scope change controlD. Scope DefinitionE. Scope verification

23 The work breakdown structure (WBS) is first developed in which scope management process? A. InitiationB. Scope planningC. Scope change controlD. ScopeDefinitionE. Scope verification

● Which of the following can be tracked using the WBS?A timeB costC performanceD scopeE None of the above.

● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.(75)A.independent resourceB.individual work loadC.work milestoneD.work package

In project management and systems engineering,()is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.A.RBSB.PBSC.GBSD.WBS

Which option best describes the features of the Personal Worklist page, as compared with AdvancedWorklist?() A. provides an overview of notificationsB. provides the capability to administer notificationsC. provides the most detailed options for searching workflowD. provides the most detailed options for searching workflow, and provides the capability to administer notifications

项目范围基线包括()A、批准的项目范围说明书、WBS及WBS字典B、项目初步范围说明书、WBS及WBS字典C、批准的项目范围说明书,WBS字典D、项目详细范围说明书、WBS

()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.A.The project charterB.The project scope statementC.The WBS dictionaryD.The activity list

The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement

( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives. A.Collecting requirements B.Defining requirements C.Creating WBS D.Requirements analysis

The creation of a work breakdown structure(WBS)is the process of ( ) the major project deliverables. A.subdividing B.assessing C.planning D.integrating

The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter B.project scope goal C.project budget D.project scope statement

( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives. A.Collecting requirements B.Defining requirementsC.Creating WBS D.Requirements analysis

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level. A.independent resource B.individual work loaD. C.work milestone D.work package

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resourceB.individual work loadC.work milestoneD.work package

Which service component in a detailed design development focuses on identification and configuration of the actual network components (routers, servers, local-area networks, and so on) to be incorporated to run and support a Cisco Unified Communications system. ()A、System Design WorkshopB、Feature and Functionality Design WorkshopC、Device-level Design WorkshopD、Physical Design Workshop

我们常说的项目责任矩阵是()A、WBS—RBSB、WBS—OBSC、WBS—CBSD、OBS—ABS

Which three of these service components are in the implement phase?()A、StagingB、Business Requirements DevelopmentC、Post Implementation Support Handoff MeetingD、Detailed Design DevelopmentE、Staff TrainingF、Incident Management

As an experienced technician, you are responsible for Technical Support in your company. You ask one of the trainees to document the layers of an existing CIS network. Which three statements best characterize this process? ()(Choose three.)A、It provides reliable input for verifying network consistency.B、It requires a network audit to support some upgrade decisions.C、It requires a network audit to support any network restructuring.D、It begins with gathering organizational input that may be inaccurate.

An administrator is configuring a new cluster and has a requirement for a notification to be generated if the /tmp File System becomes greater than 90% full. Which of the following PowerHA components will support theadministrator’s requirement?()A、Pre-defined EventsB、User-defined EventsC、Remote notification methodsD、The integration between RMC and WebSM

Which document provides guidelines to support planning and provides pre-installation steps forthe IBM System Storage DS8000?()A、Solution Assurance Product Review GuideB、DS8000 Introduction and Planning GuideC、DS8000 Installation GuideD、System Assurance Product Review Guide

Which storage subsystem provides high availability with the support for more than two processingnodes?()A、XIV and SONAS B、XIV and DS8700 C、SONAS and N7700 D、SONAS and DS8700

Which option best describes the features of the Personal Worklist page, as compared with AdvancedWorklist?()A、provides an overview of notificationsB、provides the capability to administer notificationsC、provides the most detailed options for searching workflowD、provides the most detailed options for searching workflow, and provides the capability to administer notifications

单选题The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.AsubdividingBassessingCplanningDintegrating

单选题Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()AindependentresourceBindividualworkloadCworkmilestoneDworkpackage

多选题As an experienced technician, you are responsible for Technical Support in your company. You ask one of the trainees to document the layers of an existing CIS network. Which three statements best characterize this process? ()(Choose three.)AIt provides reliable input for verifying network consistency.BIt requires a network audit to support some upgrade decisions.CIt requires a network audit to support any network restructuring.DIt begins with gathering organizational input that may be inaccurate.