Validate Scope is the process of formalizing acceptance of completed().A.project deliverablesB.WBSC.activitiesD.milestones

Validate Scope is the process of formalizing acceptance of completed().

A.project deliverables

B.WBS

C.activities

D.milestones


相关考题:

Which of the following are included as part of a scope statement?A.Project justificationB.Project deliverablesC.Project objectivesD.All of the aboveE.B and C

Which of the following is not a scope management process?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

The project charter is prepared in which scope management process?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

The work breakdown structure (WBS) is first developed in which scope management process?A . InitiationB . Scope planningC . Scope change controlD . Scope DefinitionE . Scope verification

The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(73)A. work performance informationB. scope statementC. change requestsD. process analysis

The()describes, in detail, the project's deliverables and the work required to create those deliverables. A.project scope statementB.project requirementC.project charterD.product specification

142 The project charter is prepared in which scope management process?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

144 Which of the following is not a scope management process?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A.WBS CreationB.Scope definitionC.Project acceptanceD.Scope verification

The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteriaA.work performance informationB.scope statementC.change requestsD.process analysis

The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter

The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.A.work performance informationB.scope statementC.change requestsD.process analysis

()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。A、Validate scopeB、Define scopeC、Control scopeD、Collect requirement

the () is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverablesA.verify scopeB.define scopeC.quality assuranceD.validate scope

The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).A.Project Scope StatementB.Project Management PlanC.ForecastsD.Project Charter

The inputs of developing project management plan do not include()A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes

() is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily. A.Project acceptance B.Scope verification C.Scope definition D.WBS Creation

Validate Scope is the process?of?formalizing?acceptance?of the?Complete()。A.project?deliverablesB.WBSC.activitiesD.milestones

The()process differs from the()process in that the former is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with correctness of the deliverables.A.perform Quality AssuranceB.Validate ScopeC.Control QualityD.Define Scope

( )is a process of developing a detailed description of the project and productA.collect requirementsB.Scope definitionC.validate scopeD.Control range

the ( ) is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverables. A.verify scope B.define scope C.quality assurance D.validate scope

The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter B.project scope goal C.project budget D.project scope statement

The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.A、work performance informationB、scope statementC、changerequestsD、process analysis

()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificationC、Scope definitionD、WBS Creation

单选题() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.AprojectacceptanceBscopeverificationCscopedefinitionDWBS Creation

单选题()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.AProject acceptanceBScope verificationCScope definitionDWBS Creation