70 Risk Event Status is defined as _____ .A. Risk Probability x Amount At Stake.B. the severity of the consequences.C. how likely the event is to occur with risk.D. (Cost + Benefit + Business Risk) / Insurable Risk.E. B and C
70 Risk Event Status is defined as _____ .
A. Risk Probability x Amount At Stake.
B. the severity of the consequences.
C. how likely the event is to occur with risk.
D. (Cost + Benefit + Business Risk) / Insurable Risk.
E. B and C
相关考题:
Project Risk _____ .A should not be calculated for small projects.B is the probability of each risk event minus the sum of the consequences of potential risk events.C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D cannot be quantified for first time projects.E B or D
Range estimating in determining cost risk probabilities requires _____ .A an amount of financial exposure.B risks and opportunities ranked in order of bottom line importanceC contingency requirements for expected level of confidenceD probability of cost overrun occurrencesE All of the above.
Amount at Stake is the _____ .A function of planned time/real time project costs.B risk identified in successful project completions.C (Standard Project Deviation + Expected Costs)/6D cost of investment loss + least cost to restore status quo.E inherent risk at conception altered by standard project deviations.
Risk Event Status is defined as _____ .A Risk Probability x Amount At Stake.B the severity of the consequences.C how likely the event is to occur with risk.D (Cost + Benefit + Business Risk) / Insurable Risk.E B and C
Risk event probability is defined as:A the total number of possible events divided into the expectations or frequency of the risk eventB the number of times the risk event may occurC the fraction of the total project tasks which may be affected by the risk eventD the total number of possible events divided into the consequences of the risk event.E A and B
In Project Risk Management, Risk Response may include actions to:A reduce the probability of risk eventsB change the scope, budget, schedule or quality specifications of the projectC reduce the consequences or severity of impacts of a potential risk eventD A and CE All of the above.
Total Project Risk:A should not be calculated for small projectsB is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.D A and BE A and C
Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?A liability lossB direct property lossC profit lossD personnel-related lossE B and C
Monte Carlo simulation:A Was originally developed by Dr. CarloB Is a European technique for assessing project risksC assumes the future risk events will occur at random according to predetermined probability distributionsD is a technique to stimulate create risk event resolutionE A, B and C only
Total project risk can be defined as:A the sum of the probabilities of project risks events times the sum of consequences of those risksB the sum of the products of each project risk event times its consequencesC the sum of the consequences of all project risk eventsD the sum of the probabilities of all project risk eventsE 1 - the sum of the probabilities of all project risk events.
15 Total project risk can be defined as:A. the sum of the probabilities of project risks events times the sum of consequences of those risksB. the sum of the products of each project risk event times its consequencesC. the sum of the consequences of all project risk eventsD. the sum of the probabilities of all project risk eventsE. 1 - the sum of the probabilities of all project risk events
27 Monte Carlo simulation:A. Was originally developed by Dr. CarloB. Is a European technique for assessing project risksC. assumes the future risk events will occur at random according to predetermined probability distributionsD. is a technique to stimulate create risk event resolutionE. A, B and C only
84 Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?A. liability lossB. direct property lossC. profit lossD. personnel-related lossE. B and C
122 Total Project Risk:A. should not be calculated for small projectsB. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.D. A and BE. A and C
125 In Project Risk Management, Risk Response may include actions to:A. reduce the probability of risk eventsB. change the scope, budget, schedule or quality specifications of the projectC. reduce the consequences or severity of impacts of a potential risk eventD. A and CE. All of the above
144 Risk event probability is defined as:A. the total number of possible events divided into the expectations or frequency of the risk eventB. the number of times the risk event may occurC. the fraction of the total project tasks which may be affected by the risk eventD. the total number of possible events divided into the consequences of the risk event.E. A and B
81 Amount at Stake is the _____ .A. function of planned time/real time project costs.B. risk identified in successful project completions.C. (Standard Project Deviation + Expected Costs)/6D. cost of investment loss + least cost to restore status quo.E. inherent risk at conception altered by standard project deviations
137 Range estimating in determining cost risk probabilities requires _____ .A. an amount of financial exposure.B. risks and opportunities ranked in order of bottom line importanceC. contingency requirements for expected level of confidenceD. probability of cost overrun occurrencesE. All of the above
170 Project Risk _____ .A. should not be calculated for small projects.B. is the probability of each risk event minus the sum of the consequences of potential risk events.C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D. cannot be quantified for first time projects.E. B or D
In Project Risk Management, Risk Response may include actions to:A. reduce the probability of risk eventsB. change the scope, budget, schedule or quality specifications of the projectC. reduce the consequences or severity of impacts of a potential risk eventD. A and CE. All of the above
152 Risk Event Status is defined as _____ .A. Risk Probability x Amount At Stake.B. the severity of the consequences.C. how likely the event is to occur with risk.D. (Cost + Benefit + Business Risk) / Insurable Risk.E. B and C
●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.(71)A. Quantitative Risk AnalysisB. Qualitative Risk AnalysisC. Enterprise Environmental FactorsD. Risk Management Plan
______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.A.Quantitative Risk AnalysisB.Qualitative Risk AnalysisC.Enterprise Environmental FactorsD.Risk Management Plan
● Project()is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality()A. risk B. problem C. result D. data
( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality. A.Quantitative Risk Analysis B.Qualitative Risk Analysis C.Enterprise Environmental Factors D.Risk Management Plan
()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A、Quantitative Risk AnalysisB、Qualitative Risk AnalysisC、Enterprise Environmental FactorsD、Risk Management Plan
单选题()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.AQuantitative Risk AnalysisBQualitative Risk AnalysisCEnterprise Environmental FactorsDRisk Management Plan