( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality. A.Quantitative Risk Analysis B.Qualitative Risk Analysis C.Enterprise Environmental Factors D.Risk Management Plan

( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.

A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmental Factors
D.Risk Management Plan

参考解析

解析:翻译:(71)利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。A.定量风险分析 B.定性风险分析 C.企业环境因素 D.风险管理计划

相关考题:

The purpose of project Risk Management is to:A Identify those factors that will adversely impact project objectives.B Assess the impact of adverse project factors.C Assess the probability of adverse project factors.D A and CE All of the above.

Project Risk Management is based on which of the following premises:A the future is unknown.B unknowns can result in risks or opportunities.C we cannot control risk events.D project risk impact can be measured and controlledE All of the above.

Project Risk _____ .A should not be calculated for small projects.B is the probability of each risk event minus the sum of the consequences of potential risk events.C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D cannot be quantified for first time projects.E B or D

In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:A Work breakdown structureB milestone review and schedule techniqueC cost/schedule control systemD planning programming budget systemE program and evaluation review technique

By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:A Significantly reduce project risksB eliminate project risksC provide a rational basis for better decision makingD identify risks, their impact(s), and any appropriate responsesE None of the above.

Since risk is associated with most projects, the best course of action is to:A cover all project risks by buying appropriate insuranceB ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.C avoid projects with clear and present risksD eliminate all known risks prior to the execution phase of the projectE identify various risks and implement actions to mitigate their potential impact

77 Since risk is associated with most projects, the best course of action is to:A. cover all project risks by buying appropriate insuranceB. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.C. avoid projects with clear and present risksD. eliminate all known risks prior to the execution phase of the projectE. identify various risks and implement actions to mitigate their potential impact

59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:A. Significantly reduce project risksB. eliminate project risksC. provide a rational basis for better decision makingD. identify risks, their impact(s), and any appropriate responsesE. None of the above

85 The purpose of project Risk Management is to:A. Identify those factors that will adversely impact project objectives.B. Assess the impact of adverse project factors.C. Assess the probability of adverse project factors.D. A and CE. All of the above

108 Project Risk Management is based on which of the following premises:A. the future is unknown.B. unknowns can result in risks or opportunities.C. we cannot control risk events.D. project risk impact can be measured and controlledE. All of the above

There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.A.shareB.MitigateC.TransferD.Acceptance

●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.(71)A. Quantitative Risk AnalysisB. Qualitative Risk AnalysisC. Enterprise Environmental FactorsD. Risk Management Plan

(c) Using information from the case, assess THREE risks to the Giant Dam Project. (9 marks)

● There are strategies typically deal with threats or risks that may have negative impacts on project objectives if they occur. Some other strategies are suggested to deal with risks with potentially positive impacts. (74) is a risk response strategy that may be adopted for either threats or opportunities.(74) A. ShareB. MitigateC. TransferD. Acceptance

______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.A.Quantitative Risk AnalysisB.Qualitative Risk AnalysisC.Enterprise Environmental FactorsD.Risk Management Plan

Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses

Since risk is associated with most projects,the best course of action is to (71)A.cover all project risks by buying appropriate insuranceB.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious mannerC.avoid project with clear and present riskD.identify various risks and implement actions to mitigate their potential impact

Since risk is associated with most projects,the best course of action is to ( )A.cover all project risks by buying appropriate insuranceB.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious mannerC.avoid project with clear and present riskD.identify various risks and implement actions to mitigate their potential impact

()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.A.Identity risksB.Control risksC.Plan risk responsesD.Plan risk management

Safety-management objectives of the Company should establish safeguards ______all identified risks.A.withB.withoutC.againstD.above

()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.A.identify risksB.monitor risksC.implement risks responsesD.plan risk management

May be involved in the qualitative analysis of project risks(). A.Establish probability and influence matrixB.Decision tree analysisC.Sensitivity analysisD.Modeling and simulation

Risks other()All Risks and War Risk can be covered if the extra pr- enium should be borne by the buyer.

()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A、Quantitative Risk AnalysisB、Qualitative Risk AnalysisC、Enterprise Environmental FactorsD、Risk Management Plan

Which of the following techniques is used for tracking the project risks?()A、Probability-Impact matrixB、Pareto chartC、R-ChartD、PERT (Program Evaluation and Review Technique) analysis

单选题Which of the following techniques is used for tracking the project risks?()AProbability-Impact matrixBPareto chartCR-ChartDPERT (Program Evaluation and Review Technique) analysis

单选题The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.ARiskldentificationBQuantitative Risk AnalysisCQualitative Risk AnalysisDRisk Monitoring and Control