64 The critical path in a network is the path that:A. Has the greatest degree of risk.B. Will elongate the project if the activities on this path take longer than anticipated.C. Must be completed before all other paths.D. All of the above.E. A and B only

64 The critical path in a network is the path that:

A. Has the greatest degree of risk.

B. Will elongate the project if the activities on this path take longer than anticipated.

C. Must be completed before all other paths.

D. All of the above.

E. A and B only


相关考题:

The critical path is calculated byA.subtracting the end date of task one from the start date of task two.B.determining which tasks have the least amount of total slack.C.totaling the time for all activities.D.determining the shortest path through the network.E.Determining which tasks have the most slack

The critical path in a schedule network is the path that:A.Takes the longest time to completeB.Must be done before any other tasksC.Allows some flexibility in scheduling a start time.D.Is not affected by schedule slippageE.All of the above.

Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:A.The project's schedule will be reduced by weeks.B.The available slack on the noncritical paths will increase.C.A new critical path may appear after the crash.D.All of the above.E.A and B only.

Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:A.All activities.B.Only those activities with the longest time durations.C.Those activities on the critical path begining with the longest time duration activities.D.Those activities with the greatest degree of risk.E.None of the above.

A non-critical path activity is completed in half the time. Then,A.The critical path is also reduced.B.The slack in the path containing this activity will increase.C.The total cost for this activity has decreased.D.Manpower from this activity can be assigned to other activities.E.All of the above.

The critical path in a network is the path that:A.Has the greatest degree of risk.B.Will elongate the project if the activities on this path take longer than anticipated.C.Must be completed before all other paths.D.All of the above.E.A and B only.

During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A . The project will be completed late.B . The critical path has been lengthened.C . the costs are being overrun.D . Overtime will be required to maintain the original critical path.E . None of the above.

Standard deviation of project completion is _____ .A a relationship of the uncertainty of critical path activities.B an indicator of project end date target confidenceC a function of critical path, leveling and project costs.D A and BE All of the above.

142 Activities with zero time duration are referred to as:A. Critical path activites.B. Noncritical path activities.C. Slack time activities.D. DummiesE. None of above

81 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A. The project will be completed late.B. The critical path has been lengthened.C. the costs are being overrun.D. Overtime will be required to maintain the original critical path.E. None of the above

88 A non-critical path activity is completed in half the time. Then,A. The critical path is also reduced.B. The slack in the path containing this activity will increase.C. The total cost for this activity has decreased.D. Manpower from this activity can be assigned to other activities.E. All of the above

111 Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:A. All activities.B. Only those activities with the longest time durations.C. Those activities on the critical path begining with the longest time duration activities.D. Those activities with the greatest degree of risk.E. None of the above

170 Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:A. The project's schedule will be reduced by 2 weeks.B. The available slack on the noncritical paths will increase.C. A new critical path may appear after the crash.D. All of the above.E. A and B only

181 The critical path in a schedule network is the path that:A. Takes the longest time to completeB. Must be done before any other tasksC. Allows some flexibility in scheduling a start time.D. Is not affected by schedule slippageE. All of the above

112 The schedule risk is the _____ .A. the accumulated "expected' durations which maintain project completion.B. Critical Path adjusted by "high-risk" activity float.C. highest risk path that maintains quality.D. Critical Path when calculated with "most likely" duration.E. highest risk path that contributes the most risk toward the project completion

130 Standard deviation of project completion is _____ .A. a relationship of the uncertainty of critical path activities.B. an indicator of project end date target confidenceC. a function of critical path, leveling and project costs.D. A and BE. All of the above

146 The critical path in a network is the path that:A. Has the greatest degree of risk.B. Will elongate the project if the activities on this path take longer than anticipated.C. Must be completed before all other paths.D. All of the above.E. A and B only

163 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A. The project will be completed late.B. The critical path has been lengthened.C. the costs are being overrun.D. Overtime will be required to maintain the original critical path.E. None of the above.

● The critical path is calculated byA subtracting the end date of task one from the start date of task two.B determining which tasks have the least amount of total slack.C totaling the time for all activities.D determining the shortest path through the network.E Determining which tasks have the most slack

● The critical path in a schedule network is the path that:A Takes the longest time to completeB Must be done before any other tasksC Allows some flexibility in scheduling a start time.D Is not affected by schedule slippageE All of the above.

● Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:A All activities.B Only those activities with the longest time durations.C Those activities on the critical path begining with the longest time duration activities.D Those activities with the greatest degree of risk.E None of the above.

● A non-critical path activity is completed in half the time. Then,A The critical path is also reduced.B The slack in the path containing this activity will increase.C The total cost for this activity has decreased.D Manpower from this activity can be assigned to other activities.E All of the above.

● The critical path in a network is the path that:A Has the greatest degree of risk.B Will elongate the project if the activities on this path take longer than anticipated.C Must be completed before all other paths.D All of the above.E A and B only.

A critical path for a project is the series of activities that determine( ) by which the project can be completeA.the earliest timeB.The latest timeC.The total timeD.the free time

A critical path for a project is the series of activities that determine( )by which the project can be completed.A.the earliest timeB.the latest timeC.the total timeD.the free time

In project network diagram ,the number of critical path is ( ).A.noneB.only oneC.only twoD.one or more

In?project?net work?diagram,the?number?of?critical?path?is()。A.noneB.only?oneC.only?twoD.one?or?more