47 The major difference between PERT and CPM networks is:A. PERT requires three time estimates whereas CPM requires one time estimate.B. PERT is used for construction projects whereas CPM is used for R D.C. PERT addresses only time whereas CPM also includes cost and resource availability.D. PERT requires computer solutions whereas CPM is a manual technique.E. PERT is measured in days whereas CPM uses weeks or months

47 The major difference between PERT and CPM networks is:

A. PERT requires three time estimates whereas CPM requires one time estimate.

B. PERT is used for construction projects whereas CPM is used for R & D.

C. PERT addresses only time whereas CPM also includes cost and resource availability.

D. PERT requires computer solutions whereas CPM is a manual technique.

E. PERT is measured in days whereas CPM uses weeks or months


相关考题:

The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.A.Increases.B.Is not affected byC.Does not requireD.Is heavily dependent uponE.Is the only means of determining

The first step in building a PERT/CPM network is to:A.Create a flow chartB.Determine the critical pathC.Show task relationshipsD.Create a work breakdown structureE.None of the above.

The major difference between PERT and CPM networks is:A.PERT requires three time estimates whereas CPM requires one time estimate.B.PERT is used for construction projects whereas CPM is used for R D.C.PERT addresses only time whereas CPM also includes cost and resource availability.D.PERT requires computer solutions whereas CPM is a manual technique.E.PERT is measured in days whereas CPM uses weeks or months.

PERT和CPM的区别在于PERT采用()。 A、在计算进度是采用分布均值B、使用条件和循环C、使用最可能时间来计算进度D、集中于计算关键路径

PERT与CPM的区别是()。 A.时间估计与分析B.画法不同C.组成不同D.时间参数不同

190 The first step in building a PERT/CPM network is to:A. Create a flow chartB. Determine the critical pathC. Show task relationshipsD. Create a work breakdown structureE. None of the above

101 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.A. Increases.B. Is not affected byC. Does not requireD. Is heavily dependent uponE. Is the only means of determining

129 The major difference between PERT and CPM networks is:A. PERT requires three time estimates whereas CPM requires one time estimate.B. PERT is used for construction projects whereas CPM is used for R D.C. PERT addresses only time whereas CPM also includes cost and resource availability.D. PERT requires computer solutions whereas CPM is a manual technique.E. PERT is measured in days whereas CPM uses weeks or months

有哪三种主要的图示法:( )A.AOA、PERT、CPMB.PERT、CPM、GERTC.先导、箭线、条件D.AON、AOA、PDM

● The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.A Increases.B Is not affected byC Does not requireD Is heavily dependent uponE Is the only means of determining

● The first step in building a PERT/CPM network is to:A Create a flow chartB Determine the critical pathC Show task relationshipsD Create a work breakdown structureE None of the above.

● 在软件开发中, (29) 不能用来描述项目开发的进度安排。在其他三种图中可用 (30) 动态地反映项目开发进展情况。(29)A. 甘特图 B. PERT 图 C. PERT/CPM 图 D. 鱼骨图(30)A. 甘特图 B. PERT 图 C. PERT/CPM 图 D. 鱼骨图

PERT和CPM的最根本区别是( )。A.CPM的工作逻辑关系肯定,PERT的工作逻辑关系不确定B.CPM使用最大可能工作时间估计,PERT使用加权平均时间估计C.CPM的工作必须进行,PERT的某些工作可以不进行D.CPM不允许存在回路,PERT中可以存在回路

在信息系统项目建设开发中,( )不能用来描述项目的进度安排;( )可采用来动态的放映建设的进展状况。A.甘特图B.pert 图C.pert/cpm 图D.鱼骨图A.甘特图B.pert 图C.pert/cpm 图D.鱼骨图

PERT和CPM的根本区别是( )。A.CPM的工作逻辑关系肯定,PERT的工作逻辑关系不确定 B.PERT使用了加权平均时间估算 C.CPM的工作必须进行,PERT的某些工作可以不进行 D.CPM不允许存在回路,PERT中可以存在回路

PERT与CPM的根本区别在于PERT使用了( )时间估计。A.最大可能 B.平均C.加权平均 D.最小可能

(2016年真题)PERT 与 CPM 的根本区别在于 PERT 使用了( C )时间估计。A.最大可能B.平均C.加权平均D.最小可能

分析CPM和PERT的主要的特点及区别。

目前,软件项目的进度安排的两种比较常用的方法是程序评估与审查技术(PERT)和关键路径法(CPM)。

三种主要的图示法(diagramming methods)是()A、AOA,PERT和CPMB、PERT,CPM和GERTC、前导图法、箭线图法、条件网络图法D、AON,AOA和PDM

下列哪个关于估算的说法是正确的()A、PERT比CPM更好B、PERT估算比蒙特卡洛模拟要好C、CPM对一个任务使用三个估算(最悲观、最乐观和最可能)D、蒙特卡洛模拟使用PERT公式

有哪三种主要的图示法()A、AOA、PERT、CPMB、PERT、CPM、GERTC、前导、箭线、条件D、D、AON、AOPDM

三种主要的用于项目管理的图示法是:()A、AOA、PERT和CPMB、PERT、CPM和GERTC、PDM、ADM和CDMD、AON、AOA和PDM

下列有关PERT和CPM的说法错误的是()A、通过PERT技术可以得出任何项目都有不可压缩的最小周期B、PERT可以用作逐日管理C、PERT与CPM的根本不同点在于对活动时间T的计算D、对于大型项目,PERT与CPM可以结合使用

CPM和PERT在时间的估计和分析上是相同的。

制定项目计划常用的方法有()A、工作分析结构表(WBS)B、甘特图C、ER图D、PERT图E、CPM图

单选题有哪三种主要的图示法:()AAOA、PERT、CPMBPERT、CPM、GERTC先导、箭线、条件DD、AON、AOPDM