Going from Level to Level in the work breakdown structure will result inA.Less estimating accuracyB.Better control of the projectC.Lower status reporting costsD.A greater likelihood that something will fall through the cracksE.None of the above
Going from Level to Level in the work breakdown structure will result in
A.Less estimating accuracy
B.Better control of the project
C.Lower status reporting costs
D.A greater likelihood that something will fall through the cracks
E.None of the above
相关考题:
When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA.taskB.level of effortC.sub-taskD.projectE.work package
The contractual statement of work (CSOW)A.Must be the same as the proposal statement of workB.Does not identify reporting requirementsC.Can be at a different level of detail (i.e. WBS level) than the proposal statement of workD.Identifies the contractor's organizational structure for the projectE.All of the above
The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?A.Time, schedule and cost.B.Management coordination and organization structuring.C.Work methods and accountability.D.Quality of work.E.Risk and impact decision-making.
The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:A.Work packages.B.Subtasks.C.Tasks.D.Code of accounts.E.Integration points.
Guidelines for estimating time durations include:A.Assuming a normal level of labor and equipment.B.Assuming a normal work week.C.Using consistent time unitsD.Using past actual durations as guides.E.All or part of each of the above.
The work breakdown structure, the work packages, and the company's accounting system are tied together through the:A . Code of accounts.B . Overhead rates.C . Budgeting system.D . Capital budgeting process.E . All of the above.
Which of the following would most likely increase the accuracy of estimating the project cost?A . Pricing out the work at lower levels in the work breakdown structure.B . Using historical data.C . Talking to people who have worked on similar projects.D . All of the above.E . A and C only.
The primary source document for establishing the content of the Project Status Report is:A The project charterB The Project PlanC The ASTM Project Document GuideD The summary work breakdown structure
Risk management requires an understanding that _____ .A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.B risk identification must be directly aligned with the Work Breakdown Structure.C it is merely advanced preparation for possible adverse future events.D it does not imply complete control of eventsE All of the above.
87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.B. Using historical data.C. Talking to people who have worked on similar projects.D. All of the above.E. A and C only.
106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:A. Work packages.B. Subtasks.C. Tasks.D. Code of accounts.E. Integration points
131 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:A. Code of accounts.B. Overhead rates.C. Budgeting system.D. Capital budgeting process.E. All of the above
51 Going from Level 2 to Level 4 in the work breakdown structure will result inA. Less estimating accuracyB. Better control of the projectC. Lower status reporting costsD. A greater likelihood that something will fall through the cracksE. None of the above
86 The contractual statement of work (CSOW)A. Must be the same as the proposal statement of workB. Does not identify reporting requirementsC. Can be at a different level of detail (i.e. WBS level) than the proposal statement of workD. Identifies the contractor's organizational structure for the projectE. All of the above
13 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:A. Code of accounts.B. Overhead rates.C. Budgeting system.D. Capital budgeting process.E. All of the above.
63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA. taskB. level of effortC. sub-taskD. projectE. work package
● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA taskB level of effortC sub-taskD projectE work package
● The contractual statement of work (CSOW)A Must be the same as the proposal statement of workB Does not identify reporting requirementsC Can be at a different level of detail (i.e. WBS level) than the proposal statement of workD Identifies the contractor's organizational structure for the projectE All of the above
● Going from Level 2 to Level 4 in the work breakdown structure will result inA Less estimating accuracyB Better control of the projectC Lower status reporting costsD A greater likelihood that something will fall through the cracksE None of the above
● A Work Breakdown Structure:A assures all work is identifiedB subdivides the project into manageable segmentsC provides the project sponsor with a time-phase task summaryD both A and BE All of the above.
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?A Time, schedule and cost.B Management coordination and organization structuring.C Work methods and accountability.D Quality of work.E Risk and impact decision-making.
● The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:A Work packages.B Subtasks.C Tasks.D Code of accounts.E Integration points.
● The work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the (75) .(75)A. planning elementB.work packageC.subtaskD. working interface
he work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the()A.Planning elementB.Work packageC.SubtaskD.Working interface
The work breakdown structure comprises several levels of decomposition of the total project.The lowest level of definition is always the ( ) .A.planningB.elementC.subtaskD.working interface
The following entry has been added to the syslog.conf file: *.emerg;mail,daemon.crit @ sysadmin Which of the following will result from this entry?()A、 All messages at the emerg priority level and below from all facilities and messages at the crit priority level and below from the mail and daemon facilities are sent to the TTY of the user sysadmin. B、 All messages at the emerg priority level and above from all facilities, all messages at any priority level from the mail facility, and all messages at the crit priority level and above from the daemon facilities are sent to the remote host sysadmin. C、 All messages at the emerg priority level and above from all facilities and messages at the crit priority level and above from the mail and daemon facilities are sent to the remote host sysadmin. D、 All messages at the emerg priority level and above from all facilities except for the mail facility and messages at the crit priority level and above from the daemon facility are sent to the TTY of the user sysadmin.
单选题The following entry has been added to the syslog.conf file: *.emerg;mail,daemon.crit @ sysadmin Which of the following will result from this entry?()A All messages at the emerg priority level and below from all facilities and messages at the crit priority level and below from the mail and daemon facilities are sent to the TTY of the user sysadmin. B All messages at the emerg priority level and above from all facilities, all messages at any priority level from the mail facility, and all messages at the crit priority level and above from the daemon facilities are sent to the remote host sysadmin. C All messages at the emerg priority level and above from all facilities and messages at the crit priority level and above from the mail and daemon facilities are sent to the remote host sysadmin. D All messages at the emerg priority level and above from all facilities except for the mail facility and messages at the crit priority level and above from the daemon facility are sent to the TTY of the user sysadmin.