单选题Shore power must be() during dock repair.AdisconnectedBswitched offCcut offDconnected

单选题
Shore power must be() during dock repair.
A

disconnected

B

switched off

C

cut off

D

connected


参考解析

解析: 暂无解析

相关考题:

If our captain is not in his cabin, he must be on the(驾驶台)_______.A.paint lockerB.engine roomC.bridgeD.shore

A large basin cut into the shore,closed off by a caisson,and used for dry docking of ships is known as a ______.A.slipwayB.graving dockC.ground warpD.caisson dock

If you must pump bilges while a vessel is in port,you should pump only ______.A.If discharge is led to a shore tank or bargeB.During the hours of darknessC.On the outgoing tideD.As much as is necessary

The international shore connection required on a ship is designed to ______.A.Permit discharge of waste oilB.Allow hook up of fire fighting water from a dock or another vesselC.Satisfy pollution prevention requirementsD.Allow emergency use of the fire main for deballasting

The equipment required to remove an on-deck oil spill on a barge transfering oil must either be carried on board or ______.A.on a tug standing byB.available by contract with the shore facilityC.kept at the shoreside hose connection during transferD.kept in a protected shoreside location readily accessible

If our captain is not in his cabin, he must be on the ().A、paint lockerB、engine roomC、bridgeD、shore

If our captain is not in his cabin, he must be on the(驾驶台)().A、paint lockerB、engine roomC、bridgeD、shore

单选题A large basin cut into the shore,closed off by a caisson,and used for dry docking of ships is known as a().AslipwayBgraving dockCground warpDcaisson dock

单选题A vessel is()when she is not at anchor,made fast to the shore,or aground.AunderwayBmaking wayCdead in the waterDa power driven vessel

单选题If your vessel is equipped with a radiotelephone,what must also be aboard?()ACertificate of InspectionBList of ship stationsCCopy of ship to shore channelsDRadio station license

单选题Your vessel is at a dock taking bunkers through a pipe laid down on the dock. If oil begins to flow out of a tank vent,what should you do FIRST?()AOpen the intake valve to an adjacent tankBSet out drip pans and sawdust and begin to mop up the spillCSignal the shore control point to shut downDClose the valve on the tank vent line

单选题A facility used for the discharge of a cargo of a particular hazard,such as chlorine,butane or ethane,must have what to warn water traffic of an immediate danger during fire or cargo release?()AAn emergency boat and crewBA siren or rotating flashing lightCFlashing red lights located one-half mile upstream and downstream of the facilityDBuoys with flashing lights controlled from shore,located one-half mile upstream anddownstream of the facility

单选题The ()(笨重货) must be handled by jumbo boom or shore crane.Aawkward cargoBdrummed cargoCcased cargoDheavy cargo

单选题At night while the ship is tied up to the dock,a fire breaks out in a cargo hatch. After sounding the alarm,what should the person on watch do?()ABegin fighting the fire immediatelyBAwait further orders from the MasterCLet go the lines to let the vessel drift to an anchorageDSend a person to summon the shore authorities

单选题When the dock is refilled with water after docking repair, the first work which should be done by engineers is ()Aigniting boilerBreleasing air in sea water systemCstarting generatorDcut off shore power

单选题()are located on the road panel of main switchboard.AMegohm meter, insulation light and synchroscopeBSynchroscope, synchro light and megohm meterCShore power switch, insulation light and synchroscopeDMegohm meter, insulation light and shore power switch

单选题A large basin cut into the shore,closed off by a caisson,and used for drydocking of ships is known as a().AslipwayBgraving dockCground warpDcaisson dock

单选题The equipment required to remove an on-deck oil spill on a barge transfering oil must either be arried on board or().Aon a tug standing byBavailable by contract with the shore facilityCkept at the shoreside hose connection during transferDkept in a protected shoreside location readily accessible

单选题Inspection of a vessel’s propeller during dry-dock should include ()Anoting the condition of the fairwaterBinspection of the keywayClogging inspection results in the official deck logDall of above

单选题The range of a SSB transmission is MOST affected by().Aatmospheric noise and radiated powerBthe frequency band selected and time of day or nightCinterference and position of the moonDradiated power and nearness to shore

单选题You are docking a vessel starboard side to with the assistance of two tugs.You are attempting to hold the vessel off by operating both tugs at right angles to the vessel and at full power.You must ensure that().Asteerageway is not taken offBthe bow doesn't close the dock firstCthe bow closes the dock firstDthe ship has no headway at the time

单选题When is dock survey carried out?()ADuring annual repairBUsually during dock repairCBefore sea trialDAfter 5 years from last annual survey

单选题Which of the following precautions must be taken if an electric immersion heater is used to keep the coolant in a diesel engine warm during the time the engine is secured?()AThe coolant temperature must be maintained at 180℃BThe thermostatic bypass valves must be manually opened before the engine is startedCThe pressure cap must be removed while the engine is securedDElectrical power to the heater must be secured before the cooling system is drained

单选题During the dock repair, when installing the tail shaft and propeller, who should be on the spot to supervise?()Achief engineerBthe engineerCcaptainDany member of the engine department

单选题An oceangoing ship of 400 gross tons and above must be fitted with a standard discharge shore connectionWhat is the size of the bolt circle diameter of the shore connection required to transfer oily ballast to a shore side reception facility?()A125 mmB183 mmC215 mmDIt depends on outside pipe diameter

单选题During the dock repair, each sea valve must be disassembled, cleaned and ground well.Before it reassemble the sealing surface between the valve and the valve seat should be checked by ()Achief engineerBsurveyorCthe engineerDthe technique personnel of the shipyard

单选题Which statement correctly applies to a situation where a sailing vessel is overtaking a power-driven vessel().AThe power-driven vessel must keep out of the way of the sailing vesselBA special circumstance situation existsCThe sailing vessel must keep out of the way of the power- driven vesselDThe vessel which has the other vessel to the right must keep out of the way