单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.AanalyzeBtrackClevelDextend

单选题
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.
A

analyze

B

track

C

level

D

extend


参考解析

解析: 该题的关键词为"project schedule、 baseline",其主要的语句结构为一个定语从句结构"project schedule that (主语)can serve as (谓语)a baseline to_progress",含义为"项目进度可以作为怎么样项目进展的基线",根据题意,容易判断对项目进度进行跟踪,所以选择选项B。

相关考题:

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

● The project scope/charter baseline includes:A Summary of background conditions defining the project.B Organization, authority and responsibility relationships.C Functions to be performed.D Resource requirement schedule including time estimates.E All of the above.

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend

●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.(74)A.scope statementB.activity listC.project charterD.project schedule

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule

A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A.gantt chartB.project histogramC.milestone chartD.project flowchart

In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.A.scheduleB.WBSC.SOWD.charter

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved (74) that can serve as a baseline to track progress.A.scope statementB.activity listC.project charterD.project schedule

In project time management processes,( )involves identifying and documenting the relationships between project activities.A.activity definitionB.activity sequencingC.schedule controlD.Schedule development

In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.A.scheduleB.activityC.planD.contractor@@@SXB@@@A.findingB.balanceC.allocationD.distribution

Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.A.cost management planB.risk management planC.scope management planD.management schedule

Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )A.fast trackingB.what-if scenario analysisC.resource levelingD.critical chain method

Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.A.cost management plan B.risk managementC.scope management planD.management schedule

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved () that can serve as a baseline to track progress. A.scope statementB.activity listC.project charter D.project schedule

( ) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project. A.gantt chart B.project histogram C.milestone chart D.project flowchart

Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating B.activity resource estimating, activity duration estimating, schedule development C.schedule developing, activity resource estimating, activity duration estimating D.activity resource estimating, schedule developing, activity duration estimating

Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ). A.fast tracking B.what-if scenario analysis C.resource leveling D.critical chain methoD.

Developing the project schedule is often aniterative process. It determines the planned start and finish dates for projectactivities and milestones. Schedule development can require the review andrevision of duration estimates and resource estimates to create an approvedproject schedule that can serve as a baseline to ( ) progress. A.analyze B.track C.level D.extenD.

In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.A、scheduleB、activityC、planD、contractor

In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events. A、scheduleB、WBSC、SOWD、charter

()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A、gantt chartB、project histogramC、milestone chartD、project flowchart

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.A、analyzeB、trackC、levelD、extend

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating

单选题In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.AscheduleBactivityCplanDcontractor

单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.AanalyzeBtrackClevelDextend

单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.Aactivity duration estimating, schedule developing, activity resource estimatingBactivity resource estimating, activity duration estimating, schedule developmentCschedule developing, activity resource estimating, activity duration estimatingDactivity resource estimating, schedule developing, activity duration estimating