单选题Which of the following SCSI signaling systems uses one return line for every outgoing line, is less susceptible to interference, signal degradation, crosstalk, and allows a cable length of up to 25 meters?()A SE (Single Ended)B DE (Double Ended)C LVD (Low Voltage Differential)D HVD (High Voltage Differential)

单选题A technician purchases a new 120 GB IDE hard disk to use in an old server as a swap drive. After adding the drive to the server, the technician discovers that the operating system does not detect the drive.   After rebooting the server, the technician notices the drive is missing from POST and comes to the conclusion that the BIOS needs to be updated. The technician downloads the latest version of the BIOS update from the manufacturer website.   Which action should the technician take next?()A backup the BIOS configuration to use laterB install the BIOS update from a command promptC create a bootable floppy and copy the BIOS update tools to the floppyD read the manufacturer’s guidelines and recommendations on installing the update

单选题The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()AEvaluate phase exit milestones using sufficiency criteriaBFlexible entry and exit criteria to minimize schedule delaysCQuality measures reported only to the project steering committeeDMany work teams with few members to maximize the number of deliverable hand-offs

单选题Team member listing, scheduled tasks, and risk identification are part of the:()Aproject plan.Bproject charter.Ccommunication plan.DWBS (Work Breakdown Structure).

多选题Which three should be documented after upgrading a SCSI RAID controller?()Adisk utilizationBinstallation dateCadapter baselinesDlocation slot of the RAID controllerEstatus of the adapter card installationFRAID controller information (warranty, specifications etc.)

单选题Which of the following techniques is used for tracking the project risks?()AProbability-Impact matrixBPareto chartCR-ChartDPERT (Program Evaluation and Review Technique) analysis

单选题After upgrading the SNMP (Simple Network Management Protocol) protocol, the ()can be looked up. It is a  sequence of integers that uniquely identifies a path to a managed object.A MIB (Management Information Base)B OID (ObjectIDentifier)C registerD community name

单选题A technician needs to install the first SCSI controller in an application server. The SCSI card is factory-configured with a SCSI ID of 1. Which SCSI ID should the technician configure the card before installation?()A 0B 1C 4D 7

单选题The SOW (Statement of Work) is another name for the:()AWBS (Work Breakdown Structure).Bcost benefit analysis.Crequirements specifications.Dnarrative description of the work to be accomplished.

单选题Which is the MOST effective method for generating support for your project plan?()ARequiring stakeholders to sign-off on project plan componentsBRequesting input from all stakeholders during the planning processCProviding an open line of communication regarding the projectDClearly illustrating how the project relates to the company’s objectives

单选题As a rule of thumb for QA (Quality Assurance) activities, how many hours of downstream QA (Quality Assurance) costs are saved for each hour spent on technical reviews early in the project?()AUp to 5BUp to 10CUp to 15DUp to 20

单选题Why is it important to have a final meeting on a project that has been cancelled?()ADocument lessons learnedBAssign responsibilityCClose budgetDBegin new project

单选题Which type of server is responsible for resolving NetBIOS names?()A mail serverB DNS serverC web serverD WINS serverE DHCP server

单选题Which of the following SCSI signaling systems uses one return line for every outgoing line, is less susceptible to interference, signal degradation, crosstalk, and allows a cable length of up to 25 meters?()A SE (Single Ended)B DE (Double Ended)C LVD (Low Voltage Differential)D HVD (High Voltage Differential)

单选题The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()AEvaluate phase exit milestones using sufficiency criteriaBFlexible entry and exit criteria to minimize schedule delaysCQuality measures reported only to the project steering committeeDMany work teams with few members to maximize the number of deliverable hand-offs