()risks cannot be management proactively and therefore may be assigned a management reserve.A.KnowmB.NaturalC.UnknownD.Human

()risks cannot be management proactively and therefore may be assigned a management reserve.

A.Knowm
B.Natural
C.Unknown
D.Human

参考解析

解析:本题翻译:
()风险不能主动管理,因此可能需要分配管理准备金。
A.已知B.自然C.未知D.人为
只要能翻译出题干,就很容易能得到答案,管理准备金是为了“未知-未知”的风险。也就是不能预料
还要注意,经常容易混淆的点就是应急储备管理是为了“已知-未知”的风险。既然能够已知会发生风险,就可以进行主动管理。
所以此题选择C选项。

相关考题:

The reason that cost management is so difficult in project management is that:A . Projects by definition and nature are non-recurring events and are therefore difficult to predict.B . There are no tools for identifying project tasks.C . Project managers do not care about tracking costs, as only schedules are important to all project managers.D . A and B onlyE . B and C only

There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.A . Management reserve, unplanned allowance fund.B . Management reserve, contingency.C . Contingency fund, management reserve.D . Unplanned allowance fund, budgetary reserve.E . Unplanned reserve, planned reserve.

The major difference between project and line management is that the project manager may not have any control over which basic management function?A . Decision-makingB . StaffingC . RewardingD . Tracking/monitoringE . Reviewing

Project Risk Management is based on which of the following premises:A the future is unknown.B unknowns can result in risks or opportunities.C we cannot control risk events.D project risk impact can be measured and controlledE All of the above.

78 The major difference between project and line management is that the project manager may not have any control over which basic management function?A. Decision-makingB. StaffingC. RewardingD. Tracking/monitoringE. Reviewing

108 Project Risk Management is based on which of the following premises:A. the future is unknown.B. unknowns can result in risks or opportunities.C. we cannot control risk events.D. project risk impact can be measured and controlledE. All of the above

28 The reason that cost management is so difficult in project management is that:A. Projects by definition and nature are non-recurring events and are therefore difficult to predict.B .There are no tools for identifying project tasks.C. Project managers do not care about tracking costs, as only schedules are important to all project managers.D. A and B onlyE. B and C only

(b) Draft a report suitable for inclusion in a Management Commentary for Jones and Cousin which deals with:(i) the key risks and relationships of the business (9 marks)

(d) Explain the term ‘environmental management accounting’ and the benefits that may accrue to organisationswhich adopt it. (4 marks)

(b) Explain how the use of SWOT analysis may be of assistance to the management of Diverse Holdings Plc.(3 marks)

(b) Briefly discuss how stakeholder groups (other than management and employees) may be rewarded for ‘good’performance. (4 marks)

Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses

Some members of a partnership may be very active in the management of the firm and therefore take unlimited liability.They are referred to as ___. A.general partnersB.limited partnersC.long partnersD.unlimited partners

In order to facilitate configuration and change management,manual or automated tools may be used。Tool selection should be based on the needs of the ( ).A.project manageB.CCB membersC.Project stakeholdersD.Project Management Office (PMO)

Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.A.cost management planB.risk management planC.scope management planD.management schedule

The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.A.goalsB.valuesC.needsD.Level

Safety-management objectives of the Company should establish safeguards ______all identified risks.A.withB.withoutC.againstD.above

A load line for a ship is assigned by the ______.A.Minerals Management ServiceB.Department of EnergyC.Corps of EngineersD.A recognized classification society approved by the Coast Guard

A load line of a ship is assigned by ______.A.Minerals Management ServiceB.Department of EnergyC.Corps of EngineersD.A recognized classification society approved

Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.A.cost management plan B.risk managementC.scope management planD.management schedule

() risks cannot be management proactively and therefore may be assigned a management reserve.( )不能主动管理风险,因此可以分配管理准备金。A.Known已知B.Natural自然C.Unknown未知D.Human人为

()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.A.identify risksB.monitor risksC.implement risks responsesD.plan risk management

Which of the following statements about a Master Catalog is FALSE?()A、The Master Catalog must be a proper tree.B、The product management tools work with a Master Catalog.C、A product cannot belong to more than one category.D、A store may have more than one Master Catalog.

单选题Which of the following statements about a Master Catalog is FALSE?()AThe Master Catalog must be a proper tree.BThe product management tools work with a Master Catalog.CA product cannot belong to more than one category.DA store may have more than one Master Catalog.

单选题A load line of a ship is assigned by the().Aminerals management serviceBDepartment of energyCcorps of engineersDa recognized classification socitey approved

单选题A load line for a ship is assigned by the().AMinerals Management ServiceBDepartment of EnergyCCorps of EngineersDA recognized classification society approved by the Coast Guard

单选题Which of the following is the technology that helps organizations to reduce legal risks associated with e-mail?()AInformation Rights ManagementBJoumalingCLegal disclaimerDMessaging Records Management